10236 W CHARING CROSS ROAD 90024
Certificate Information: 10236 W CHARING CROSS ROAD 90024
- Application / Permit
- 20020-20000-02345
- Plan Check / Job No.
- B20VN14507
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- UNDERGROUND GENERATOR VAULT WITH MAT SLAB FOUNDATION ON PILES. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/17/2021
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | TROY DEGUZMAN |
| Corrections Issued | 11/28/2020 | TROY DEGUZMAN |
| Quality Review Completed | 11/30/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 11/30/2020 | APPLICANT |
| Applicant returned to address corrections | 1/14/2021 | TROY DEGUZMAN |
| Plan Check Approved | 2/17/2021 | TROY DEGUZMAN |
| Issued | 2/17/2021 | APPLICANT |
| Permit Finaled | 10/8/2024 | RICHARD STEINBACH |
| CofO Issued | 10/8/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/8/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/13/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 1/13/2021 | TROY DEGUZMAN |
Contact Information
| Architect | Landry,, Richard; Lic. No.: C21848 | 1818 S.SEPULVEDA BLVD LOS ANGELES, CA 90025 |
| Contractor | Owner-Builder | , |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/6/2021 | Partial Approval | MATT KELLERMAN |
| Piling/Pier/Caisson | 7/6/2021 | Partial Approval | MATT KELLERMAN |
| Pre-Inspection | 7/6/2021 | Partial Approval | MATT KELLERMAN |
| Piling/Pier/Caisson | 7/8/2021 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 7/20/2021 | Conditional Approval | MATT KELLERMAN |
| Piling/Pier/Caisson | 7/23/2021 | Partial Approval | MATT KELLERMAN |
| Piling/Pier/Caisson | 7/28/2021 | Conditional Approval | MATT KELLERMAN |
| Piling/Pier/Caisson | 8/19/2021 | Partial Approval | MATT KELLERMAN |
| Reinforced Concrete Frame | 9/22/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 10/23/2021 | Conditional Approval | MATT KELLERMAN |
| Reinforced Concrete Frame | 11/9/2021 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 8/16/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/18/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 5/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 5/15/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Structural Steel Frame | 7/11/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 10/3/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 10/3/2024 | Approved | CHRISTOPHER WILSON |