13481 W CHELTENHAM DR 91423
Certificate Information: 13481 W CHELTENHAM DR 91423
- Application / Permit
- 20020-20000-02075
- Plan Check / Job No.
- B20VN12915
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (2) NEW 6'-0" MAX. HIGH RETAINING WALLS (12'-0" MAX.), 228 FT. LENGTH, TO CREATE LEVEL REAR YARD AREA. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- Issued on 12/22/2020
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | COLIN LOREDO |
| Corrections Issued | 11/10/2020 | COLIN LOREDO |
| Quality Review Completed | 11/25/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/30/2020 | APPLICANT |
| Plan Check Approved | 12/21/2020 | COLIN LOREDO |
| Issued | 12/22/2020 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/29/2020 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
| Geologist | Kennedy,, Cameron L; Lic. No.: EG2631 | 25208 W DOLCE COURT STEVENSON RANCH, CA 91381 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 2/4/2021 | Approved | TIMOTHY POWELL |
| Deputy Grading | 2/5/2021 | Approved | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 2/16/2021 | Not Ready for Inspection | TIMOTHY POWELL |
| Piling/Pier/Caisson | 2/16/2021 | Corrections Issued | TIMOTHY POWELL |
| Piling/Pier/Caisson | 2/24/2021 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Approved | VASIL MIHALEV |
| Footing/Foundation/Slab | 4/21/2021 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 4/22/2021 | Conditional Approval | BRIAN OLSON |
| Reinforced Concrete Frame | 6/16/2021 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 7/2/2021 | Approved | ALEXANDER HELFER |
| Grading Pre-Inspection | 7/14/2021 | Partial Approval | MANUEL TEJADA |
| Masonry Wall/Backfill | 7/14/2021 | No Access for Inspection | MANUEL TEJADA |