4132 N WITZEL DR 91423

Certificate Information: 4132 N WITZEL DR 91423

Application / Permit
20020-20000-01839
Plan Check / Job No.
B20VN11420
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
(N) 6FT HIGH MAX (59LF) RETAINING WALL ON PILES PER ENG'R DESIGN
Permit Issued
Issued on 9/28/2023
Issuing Office
Valley
Current Status
Permit Finaled on 4/5/2024

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 NILOOFAR MEHRAIN
Corrections Issued 10/1/2020 NILOOFAR MEHRAIN
Quality Review Completed 10/1/2020 CHON CHIO KUO
Building Plans Picked Up 1/13/2021 APPLICANT
Applicant returned to address corrections 12/20/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/2/2023 NILOOFAR MEHRAIN
Plan Check Approved 8/25/2023 NILOOFAR MEHRAIN
Issued 9/28/2023 APPLICANT
Permit Finaled 4/4/2024 MANUEL TEJADA

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 8/10/2023 CALOSHA APPROVED
Grading Pre-Inspection Cleared 8/10/2023 NILOOFAR MEHRAIN
Eng Process Fee Ord 176,300 Cleared 8/18/2023 JOHN LIN
Roof/Waste drainage to street Cleared 8/18/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

MATTHEW JENKINS, (818) 374-4357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/28/2023 Approved MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 11/28/2023 Partial Approval MANUEL TEJADA
Deputy Reinf. Concrete 11/29/2023 Approved ROBERT PINA
Deputy Reinf. Concrete 11/30/2023 Approved MANUEL TEJADA
Footing/Foundation/Slab 11/30/2023 Conditional Approval MANUEL TEJADA
Deputy Reinf. Concrete 12/1/2023 Approved MANUEL TEJADA
Footing/Foundation/Slab 12/1/2023 Approved MANUEL TEJADA
Final 12/4/2023 Not Ready for Inspection MANUEL TEJADA
Final 4/4/2024 Permit Finaled MANUEL TEJADA