4132 N WITZEL DR 91423
Certificate Information: 4132 N WITZEL DR 91423
- Application / Permit
- 20020-20000-01839
- Plan Check / Job No.
- B20VN11420
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) 6FT HIGH MAX (59LF) RETAINING WALL ON PILES PER ENG'R DESIGN
- Permit Issued
- Issued on 9/28/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/5/2024
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/1/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/1/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/13/2021 | APPLICANT |
| Applicant returned to address corrections | 12/20/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/2/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/25/2023 | NILOOFAR MEHRAIN |
| Issued | 9/28/2023 | APPLICANT |
| Permit Finaled | 4/4/2024 | MANUEL TEJADA |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 8/10/2023 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 8/10/2023 | NILOOFAR MEHRAIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2023 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 8/18/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 11/28/2023 | Approved | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Partial Approval | MANUEL TEJADA |
| Deputy Reinf. Concrete | 11/29/2023 | Approved | ROBERT PINA |
| Deputy Reinf. Concrete | 11/30/2023 | Approved | MANUEL TEJADA |
| Footing/Foundation/Slab | 11/30/2023 | Conditional Approval | MANUEL TEJADA |
| Deputy Reinf. Concrete | 12/1/2023 | Approved | MANUEL TEJADA |
| Footing/Foundation/Slab | 12/1/2023 | Approved | MANUEL TEJADA |
| Final | 12/4/2023 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 4/4/2024 | Permit Finaled | MANUEL TEJADA |