2939 S GILMERTON AVE 90064

Certificate Information: 2939 S GILMERTON AVE 90064

Application / Permit
20020-20000-01763
Plan Check / Job No.
B20VN10774
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
ONE (N) CMU RETAINING WALL [H=6' MAX RETAINING, L=62'] (9.5' MAX HEIGHT INCLUDING GUARDRAIL) ON SOUTH SIDE OF PROPERTY AND PORTION OF THE WALL ON EAST, WEST SIDE OF PROPERTY ALL WORK PER ENGINERING
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
Permit Finaled on 3/18/2022

Permit Application Status History

Submitted 8/20/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 9/16/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/29/2020 OMID HEDAYAT
Building Plans Picked Up 10/5/2020 APPLICANT
Plan Check Approved 11/19/2020 SEWADA ZADOORAN MILAGARDI
Issued 12/1/2020 APPLICANT
Permit Closed-Status Void 12/3/2020 JONATHAN HOM
Re-Activate Permit 12/4/2020 JONATHAN HOM
Permit Finaled 3/17/2022 JONATHAN HOM

Permit Application Clearance Information

Specific Plan Cleared 10/6/2020 DYLAN SITTIG
ZI Cleared 10/6/2020 DYLAN SITTIG
Eng Process Fee Ord 176,300 Cleared 10/15/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 10/15/2020 HISASHI KOBAYAKAWA
Specific Plan Cleared 10/16/2020 LOUIS ORTEGA
ZI Cleared 10/16/2020 LOUIS ORTEGA
Grading Pre-Inspection Cleared 11/19/2020 SEWADA ZADOORAN MILAGARDI

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/3/2020 Partial Inspection JONATHAN HOM
Footing/Foundation/Slab 12/3/2020 Not Ready for Inspection JONATHAN HOM
Footing/Foundation/Slab 12/10/2020 Partial Approval JONATHAN HOM
Masonry Wall/Backfill 12/15/2020 Approved KIRK LINKLATER
Final 3/10/2021 Not Ready for Inspection BRIAN OLSON
Final 3/17/2022 Permit Finaled JONATHAN HOM