4246 N LEVITT LANE 91403
Certificate Information: 4246 N LEVITT LANE 91403
- Application / Permit
- 20020-20000-01759
- Plan Check / Job No.
- B20VN10751
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- PROPOSED 12' HIGH X 223' IN LENGTH RETAINING WALL.
- Permit Issued
- Issued on 5/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/13/2023
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | RAPHAEL ROSAS |
| Corrections Issued | 9/14/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 9/14/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 9/15/2020 | APPLICANT |
| Applicant returned to address corrections | 11/17/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/17/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 5/13/2021 | RAPHAEL ROSAS |
| Issued | 5/13/2021 | APPLICANT |
| Permit Finaled | 11/9/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 11/30/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 11/30/2020 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/22/2020 | ADRIAN CASTRO |
| Excavation more than 5-ft deep | Cleared | 3/17/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/5/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/20/2021 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Partial Approval | TIMOTHY POWELL |
| Special/Order Compliance | 8/18/2021 | Approved | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 1/24/2022 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 4/21/2022 | Partial Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Partial Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 5/11/2022 | Partial Approval | CHARLES POWELL |
| Deputy Reinf. Concrete | 5/12/2022 | Approved | MANUEL TEJADA |
| Deputy Reinf. Concrete | 5/13/2022 | Approved | VASIL MIHALEV |
| Final | 11/2/2023 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 11/9/2023 | Permit Finaled | MANUEL TEJADA |