9472 W CHEROKEE LANE 90210

Certificate Information: 9472 W CHEROKEE LANE 90210

Application / Permit
20020-20000-00916
Plan Check / Job No.
B20VN05982
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Fence Wall
Work Description
REPLACE (E) BLOCK WALL WITH NEW BLOCK WALL ON PILES (MAX HEIGHT = 6'; LENGTH = 87'-6 1/2")
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
Permit Finaled on 6/16/2023

Permit Application Status History

Submitted 4/28/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 SEAN SHAHMIRI
Corrections Issued 5/21/2020 SEAN SHAHMIRI
Quality Review Completed 6/4/2020 OMID HEDAYAT
Building Plans Picked Up 6/4/2020 APPLICANT
Applicant returned to address corrections 8/13/2020 SEAN SHAHMIRI
Applicant returned to address corrections 11/23/2020 SEAN SHAHMIRI
Applicant returned to address corrections 1/19/2021 SEAN SHAHMIRI
Plan Check Approved 2/19/2021 SEAN SHAHMIRI
Applicant returned to address corrections 2/22/2021 SEAN SHAHMIRI
Issued 2/26/2021 APPLICANT
Permit Finaled 6/15/2023 RAUL BARAJAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/19/2021 SEAN SHAHMIRI

Contact Information

Contractor Haynie Tim; Lic. No.: 980472-B 531 MAIN STREET #406      EL SEGUNDO, CA 90245
Engineer Rybak,, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Zangoli,, Fabio; Lic. No.: S6191 13245 FIJI WY UNIT J      MARINA DEL REY, CA 90292

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2022 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 5/17/2022 Partial Approval RAUL BARAJAS
Pre-Inspection 5/17/2022 Corrections Issued RAUL BARAJAS
Piling/Pier/Caisson 5/24/2022 Approved RAUL BARAJAS
Footing/Foundation/Slab 7/25/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 7/25/2022 Partial Approval RAUL BARAJAS
Masonry Wall/Backfill 8/10/2022 Partial Approval RYAN SALAZAR
Masonry Wall/Backfill 8/26/2022 Approved RAUL BARAJAS
Final 6/15/2023 Permit Finaled RAUL BARAJAS
Green Building Final 6/15/2023 Approved RAUL BARAJAS