14222 W TIARA ST 91401

Certificate Information: 14222 W TIARA ST 91401

Application / Permit
20020-20000-00776
Plan Check / Job No.
B20VN05293
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Fence Wall
Work Description
NEW 6' HIGH X 185' LONG BLOCK WALL PER CITY STANDARD DETAIL
Permit Issued
Issued on 5/6/2020
Issuing Office
Valley
Current Status
Permit Finaled on 9/9/2021

Permit Application Status History

Submitted 4/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 ROSENDO MEDINA
Corrections Issued 4/17/2020 ROSENDO MEDINA
Plan Check Approved 5/6/2020 ROSENDO MEDINA
Issued 5/6/2020 LADBS
Permit Finaled 9/9/2021 CAMERON CHABAN

Permit Application Clearance Information

"Q" conditions Cleared 4/28/2020 LAUREN PADICK
Construction near power lines Cleared 4/30/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/18/2020 Not Ready for Inspection ANDREW DORSO
Pre-Inspection 5/18/2020 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 5/20/2020 Corrections Issued DANNY RODRIGUEZ
Pre-Inspection 5/21/2020 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 5/26/2020 Partial Approval ROBERT DAVIS
Pre-Inspection 5/29/2020 Partial Approval JOHN KITCKO
Pre-Inspection 6/2/2020 Partial Inspection ANDREW DORSO
Pre-Inspection 6/9/2020 Approved JONATHAN QUACH
Final 6/16/2020 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 6/23/2020 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 7/6/2020 Partial Inspection ROBERT DAVIS
Pre-Inspection 7/23/2020 Corrections Issued ANDREW DORSO
Final 9/3/2021 Not Ready for Inspection CAMERON CHABAN
Final 9/9/2021 Permit Finaled CAMERON CHABAN