3535 N HILLVIEW PL 90032

Certificate Information: 3535 N HILLVIEW PL 90032

Application / Permit
20020-20000-00644
Plan Check / Job No.
B20VN04785
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW 103 FT LONG X 6 FT HIGH ( 6 FT HIGH MAX ABOVE THE NATURAL GRADE IN THE REQUIRED SIDE YARD), ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/26/2023
Issuing Office
Valley
Current Status
Permit Finaled on 6/6/2025

Permit Application Status History

Submitted 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 RARES BODEA
Green Plans Picked Up 4/17/2020 APPLICANT
Corrections Issued 4/23/2020 RARES BODEA
Quality Review Completed 4/30/2020 STEVEN KIM
Building Plans Picked Up 4/30/2020 APPLICANT
Applicant returned to address corrections 7/15/2020 RARES BODEA
Applicant returned to address corrections 10/24/2022 RARES BODEA
Applicant returned to address corrections 12/13/2022 RARES BODEA
Applicant returned to address corrections 1/23/2023 RARES BODEA
Applicant returned to address corrections 2/1/2023 RARES BODEA
Plan Check Approved 2/3/2023 RARES BODEA
Issued 4/26/2023 APPLICANT
Permit Finaled 6/5/2025 RAMAZANALI ALMASI

Permit Application Clearance Information

"D" conditions Cleared 4/9/2021 JASON CHAN
"Q" conditions Cleared 4/9/2021 JASON CHAN
ZI Cleared 4/9/2021 JASON CHAN
Grading Pre-Inspection Cleared 10/24/2022 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2023 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 11/13/2023 Approved ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 11/22/2023 Corrections Issued ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 11/28/2023 Partial Approval ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 12/7/2023 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 12/12/2023 Approved ROBERT HUGHES
Footing/Foundation/Slab 1/19/2024 Partial Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 2/13/2024 Partial Approval JONATHAN HOM
Deputy Reinf. Concrete 2/16/2024 Conditional Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 3/5/2024 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 3/15/2024 Partial Approval LANNY MERRICK
Footing/Foundation/Slab 3/15/2024 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 3/22/2024 Conditional Approval LANNY MERRICK
Grading Pre-Inspection 4/2/2024 Not Ready for Inspection LANNY MERRICK
Deputy Reinf. Concrete 6/7/2024 No Result Entered ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 6/24/2024 Partial Approval LANNY MERRICK
Masonry Wall/Backfill 7/24/2024 Partial Approval LANNY MERRICK
Deputy Reinf. Concrete 8/27/2024 Conditional Approval LANNY MERRICK
Masonry Wall/Backfill 8/28/2024 Partial Inspection JONATHAN HOM
Final 4/18/2025 Corrections Issued RUSSELL BONVOULOIR
Final 5/7/2025 Not Ready for Inspection RAMAZANALI ALMASI
Final 6/5/2025 Permit Finaled RAMAZANALI ALMASI