2507 N MICHELTORENA ST 90039
Certificate Information: 2507 N MICHELTORENA ST 90039
- Application / Permit
- 20020-20000-00326
- Plan Check / Job No.
- B20VN02375
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW (1) RETAINING WALL 8'8" HIGH X 114 FT LONG AND (1) RETAINING WALL 6'8" HIGH X 66 FT LONG (6 FT MAX ABOVE NATURAL GRADE IN THE REQUIRED REAR AND SIDE YARD ), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Valley
- Current Status
- Issued on 3/10/2021
Permit Application Status History
| Submitted | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | RARES BODEA |
| Corrections Issued | 2/29/2020 | RARES BODEA |
| Quality Review Completed | 3/3/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/5/2020 | APPLICANT |
| Plan Check Approved | 3/5/2021 | RARES BODEA |
| Issued | 3/10/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | CECILIO NAVARRO |
| Miscellaneous | Cleared | 6/18/2020 | TERRY PHAN |
| ZA Case | Cleared | 6/30/2020 | LAUREN PADICK |
| Landscape for retaining wall | Cleared | 7/10/2020 | LAUREN PADICK |
| Roof/Waste drainage to street | Cleared | 7/10/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 8/3/2020 | RARES BODEA |
Contact Information
| Contractor | Mid Valley Landscaping; Lic. No.: 776643-C27 | 14334 POLK ST SYLMAR, CA 91342 |
| Engineer | Shubeck,, Robert James; Lic. No.: GE773 | 60 HACKAMORE LANE BELL CANYON, CA 91307 |
Inspector Information
| LANNY MERRICK, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 7/2/2021 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 7/20/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Footing/Foundation/Slab | 7/21/2021 | Partial Approval | ROBERT HUGHES |
| Masonry Wall/Backfill | 8/9/2021 | Partial Approval | ROBERT HUGHES |
| Final | 2/14/2022 | Not Ready for Inspection | ROBERT HUGHES |