443 S LEVERING AVE 90024
Certificate Information: 443 S LEVERING AVE 90024
- Application / Permit
- 20020-20000-00255
- Plan Check / Job No.
- B20VN01642
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW (5'-9"HT x 50LF) COURTYARD RETAINING WALL. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/27/2020
- Issuing Office
- Current Status
- Permit Finaled on 9/23/2022
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Green Plans Picked Up | 2/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | TROY DEGUZMAN |
| Corrections Issued | 2/25/2020 | TROY DEGUZMAN |
| Quality Review Completed | 2/27/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 2/28/2020 | APPLICANT |
| Applicant returned to address corrections | 4/8/2020 | TROY DEGUZMAN |
| Plan Check Approved | 7/24/2020 | TROY DEGUZMAN |
| Issued | 7/27/2020 | APPLICANT |
| Permit Finaled | 9/23/2022 | CARLOS MATAMOROS |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/6/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 4/6/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Javadi-Koma,, Shahram; Lic. No.: C69497 | 6701 ETON AVE APT 115 CANOGA PARK, CA 91303 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/9/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/10/2020 | Approved | JOHNNY MIRANDA |
| Masonry Wall/Backfill | 11/18/2020 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/25/2020 | Partial Approval | KEVIN SARGSYAN |
| Masonry Wall/Backfill | 12/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Masonry Wall/Backfill | 12/3/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2020 | Approved | CARLOS MATAMOROS |
| Final | 9/23/2022 | Permit Finaled | CARLOS MATAMOROS |
| Reinforced Masonry Frame | 9/23/2022 | Approved | CARLOS MATAMOROS |
| Structural Steel Frame | 9/23/2022 | Approved | CARLOS MATAMOROS |