764 N PATTERSON PL 90272

Certificate Information: 764 N PATTERSON PL 90272

Application / Permit
20020-20000-00218
Plan Check / Job No.
B20VN01402
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Shoring (Temporary)
Work Description
TEMPORARY SHORING
Permit Issued
Issued on 12/7/2020
Issuing Office
Valley
Current Status
Permit Finaled on 11/9/2021

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 MARVEL DELACRUZ
Corrections Issued 2/23/2020 MARVEL DELACRUZ
Quality Review Completed 2/26/2020 GUANG MIN TUNG
Building Plans Picked Up 2/27/2020 APPLICANT
Applicant returned to address corrections 3/5/2020 MARVEL DELACRUZ
Applicant returned to address corrections 7/2/2020 MARVEL DELACRUZ
Applicant returned to address corrections 9/30/2020 MARVEL DELACRUZ
Plan Check Approved 10/2/2020 MARVEL DELACRUZ
Issued 12/7/2020 APPLICANT
Permit Finaled 11/8/2021 ANDREW NAVE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Voshall Construction Inc; Lic. No.: 920839-B 9909 TOPANGA CANYON #102      CHATSWORTH, CA 91311
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Purkis,, David Alan; Lic. No.: C42810 32521 CARRETERRA DR      SAN JUAN CAPISTRANO, CA 92675

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/10/2020 Approved ANDREW NAVE
Deputy Grading 12/17/2020 Approved ROBERT SHELLY
Deputy Grading 12/18/2020 Approved ROBERT SHELLY
Piling/Pier/Caisson 12/18/2020 Partial Approval CHRIS CHRISTENSEN
Deputy Grading 12/21/2020 Approved ROBERT SHELLY
Deputy Grading 12/22/2020 Approved ROBERT SHELLY
Deputy Grading 12/23/2020 Approved ROBERT SHELLY
Deputy Grading 12/24/2020 Approved ROBERT SHELLY
Deputy Grading 12/30/2020 Approved ROBERT SHELLY
Deputy Grading 12/30/2020 Corrections Issued ROBERT SHELLY
Deputy Grading 12/31/2020 Approved ROBERT SHELLY
Deputy Grading 1/4/2021 Corrections Issued ROBERT SHELLY
Deputy Grading 1/5/2021 Conditional Approval ANDREW NAVE
Deputy Grading 1/6/2021 Approved ROBERT SHELLY
Deputy Grading 1/7/2021 Conditional Approval ANDREW NAVE
Deputy Grading 1/11/2021 Corrections Issued ROBERT SHELLY
Deputy Grading 1/12/2021 Approved ROBERT SHELLY
Deputy Grading 1/13/2021 Approved ROBERT SHELLY
Deputy Grading 1/14/2021 Approved ROBERT SHELLY
Deputy Grading 1/15/2021 Approved ROBERT SHELLY
Deputy Grading 1/20/2021 Approved ROBERT SHELLY
Deputy Grading 1/21/2021 Approved ROBERT SHELLY
Deputy Grading 1/22/2021 Approved ROBERT SHELLY
Final 2/17/2021 Partial Approval ANDREW NAVE
Final 11/8/2021 Permit Finaled ANDREW NAVE