11922 W TABOR ST 90066

Certificate Information: 11922 W TABOR ST 90066

Application / Permit
20020-20000-00192
Plan Check / Job No.
B20VN01243
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
PROPOSED NEW 12' HIGH CONCRETE RETAINING WALL. L = 106' (NO EXCAVATION SHALL COMMENCE PRIOR TO 5/29/20)
Permit Issued
Issued on 6/30/2020
Issuing Office
Current Status
Permit Finaled on 6/24/2021

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 HAYATO TSUCHIYA
Corrections Issued 2/24/2020 HAYATO TSUCHIYA
Quality Review Completed 2/24/2020 ABDUL CHEGENI
Building Plans Picked Up 2/26/2020 APPLICANT
Applicant returned to address corrections 5/8/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 5/22/2020 HAYATO TSUCHIYA
Plan Check Approved 6/30/2020 MARJAN SHENASI
Issued 6/30/2020 APPLICANT
Permit Finaled 6/23/2021 AL GAMBLE

Permit Application Clearance Information

Landscape for retaining wall Cleared 3/16/2020 DANG NGUYEN
Grading Pre-Inspection Cleared 5/10/2020 HAYATO TSUCHIYA
Construction near power lines Cleared 6/7/2020 RIDWAN HARDY
Construction within easement Cleared 6/7/2020 RIDWAN HARDY

Contact Information

Contractor Kravitz Oded General Contractor Inc; Lic. No.: 1009679-B 3246 VETERAN AVE      LOS ANGELES, CA 90034
Engineer Cohanfard,, Albert; Lic. No.: C45408 910 S BEDFORD ST 304      LOS ANGELES, CA 90035
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Salehipour,, Sassan Abolghasem; Lic. No.: C44172 1290 NORTH LAKE AVENUE STE 204      PASADENA, CA 91104

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/16/2020 Partial Approval JUSTIN CURTIS
Footing/Foundation/Slab 7/30/2020 Corrections Issued MATTHEW JENKINS
Footing/Foundation/Slab 7/30/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/3/2020 Partial Inspection MATTHEW JENKINS
Excavation/Setback/Form/Re-Bar 8/4/2020 Conditional Approval MATTHEW JENKINS
Footing/Foundation/Slab 9/15/2020 Partial Inspection MATTHEW JENKINS
Footing/Foundation/Slab 9/30/2020 Partial Inspection MATTHEW JENKINS
Footing/Foundation/Slab 10/2/2020 Partial Approval MATTHEW JENKINS
Final 3/25/2021 Not Ready for Inspection MATTHEW JENKINS
Final 5/13/2021 Not Ready for Inspection MATTHEW JENKINS
Final 5/28/2021 Partial Inspection JONATHAN HOM
Final 6/17/2021 Not Ready for Inspection AL GAMBLE
Final 6/23/2021 Permit Finaled AL GAMBLE