7425 N WISCASSET DR 91304
Certificate Information: 7425 N WISCASSET DR 91304
- Application / Permit
- 20020-20000-00179
- Plan Check / Job No.
- B20VN01080
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- PROPOSED NEW RETAINING WALL AT FRONT. L = 80', HT = 7'4". SEE COMMENTS.
- Permit Issued
- Issued on 5/28/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/15/2020
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 1/24/2020 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/24/2020 | APPLICANT |
| Applicant returned to address corrections | 4/28/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/20/2020 | HAYATO TSUCHIYA |
| Issued | 5/28/2020 | LADBS |
| Permit Finaled | 9/14/2020 | ALEXANDER ANDREWS |
Permit Application Clearance Information
| Tract Map conditions | Cleared | 2/28/2020 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 2/28/2020 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 2/28/2020 | HERMINIGILDO AGUSTIN |
| Low Impact Development | Cleared | 3/5/2020 | ANDRES COVARRUBIAS |
| Construction near power lines | Cleared | 3/6/2020 | TORI CHEN |
| Construction within easement | Cleared | 3/6/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/16/2020 | GUILLERMO PETRA |
| Work Adjacent to Public Way | Cleared | 3/16/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ibarra,, Marco Antonio; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Fishburn,, Scott David; Lic. No.: EG2114 | 1545 VICTORY BLVD. GLENDALE, CA 91201 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/25/2020 | Conditional Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 6/26/2020 | Corrections Issued | ALEXANDER ANDREWS |
| Footing/Foundation/Slab | 6/30/2020 | Approved | ALEXANDER ANDREWS |
| Reinforced Concrete Frame | 7/23/2020 | Partial Approval | ALEXANDER ANDREWS |
| Final | 9/14/2020 | Permit Finaled | ALEXANDER ANDREWS |