6715 S LA TIJERA BLVD 90045
Certificate Information: 6715 S LA TIJERA BLVD 90045
- Application / Permit
- 20020-10000-02741
- Plan Check / Job No.
- B20LA24235
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- New parking light pole
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/5/2021
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2021 | SINA KHOSRAVI |
| Corrections Issued | 1/5/2021 | SINA KHOSRAVI |
| Plan Check Approved | 1/13/2021 | SINA KHOSRAVI |
| Issued | 1/13/2021 | APPLICANT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Permit Finaled | 2/4/2021 | ALAN NOVAK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Wang,, Gary H; Lic. No.: C32569 | 1000 CORPORATE CENTER DR SUITE 550 MONTEREY PARK, CA 91754 |
| Contractor | Taslimi Construction Co Inc; Lic. No.: 475159-B | 1805 COLORADO AVENUE SANTA MONICA, CA 90404 |
| Engineer | Kwei,, Peter; Lic. No.: C72100 | 1306 N HAWTHORN WY AZUSA, CA 91702 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/15/2021 | Corrections Issued | NICK LAROCCA |
| Final | 1/20/2021 | Not Ready for Inspection | ALAN NOVAK |
| Footing/Foundation/Slab | 1/26/2021 | Approved | JEFF BYTHEWAY |
| Final | 2/4/2021 | Permit Finaled | ALAN NOVAK |