12051 W VENTURA BLVD 91604

Certificate Information: 12051 W VENTURA BLVD 91604

Application / Permit
20020-10000-02506
Plan Check / Job No.
B20LA21424
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
ePlan accessible ramps, and a retaining wall.
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
Permit Finaled on 9/6/2021

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 LARRY LEE
Corrections Issued 11/24/2020 LARRY LEE
Applicant returned to address corrections 3/1/2021 LARRY LEE
Plan Check Approved 4/4/2021 LARRY LEE
Issued 5/13/2021 APPLICANT
Permit Finaled 9/3/2021 ROBERT DAVIS

Permit Application Clearance Information

Miscellaneous Cleared 3/25/2021 DANIEL CORONADO
Miscellaneous Cleared 3/25/2021 DANIEL CORONADO
ZI Cleared 3/25/2021 DANIEL CORONADO
Miscellaneous Cleared 4/1/2021 CORREY KITCHENS
Specific Plan Cleared 4/1/2021 CORREY KITCHENS

Contact Information

Contractor S V W; Lic. No.: 904878-B 122 LAFAYETTE AVENUE      LAUREL, MD 20707
Engineer Stevenson,, Carel Theodore; Lic. No.: C68555 34877 WILDWOOD CANYON RD      YUCAIPA, CA 92399
Engineer Vincent,, Travis Paul; Lic. No.: NA37356       ,

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/21/2021 Partial Approval ROBERT DAVIS
Reinforced Concrete Frame 5/21/2021 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 5/28/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 6/2/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 6/4/2021 Partial Approval ROBERT DAVIS
Masonry Wall/Backfill 6/4/2021 Approved ROBERT DAVIS
Final 9/3/2021 Permit Finaled ROBERT DAVIS
Reinforced Concrete Frame 9/3/2021 Approved ROBERT DAVIS