7965 W FAREHOLM DR 90046
Certificate Information: 7965 W FAREHOLM DR 90046
- Application / Permit
- 20020-10000-02482
- Plan Check / Job No.
- G20LA00256
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- TO CONSTRUCT 155 L.F OF PILE SUPPORTED RETAINING WALL AS PART OF SLOPE REPAIR PER ORDER TO COMPLY. 2 of 2
- Permit Issued
- Issued on 3/19/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/26/2026
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | DAN RYAN EVANGELISTA |
| Corrections Issued | 11/25/2020 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 2/26/2025 | DAN RYAN EVANGELISTA |
| Issued | 3/19/2025 | APPLICANT |
| Permit Finaled | 1/26/2026 | ROBERT PINA |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 12/14/2020 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2020 | RENZ SORIANO |
| Permit | Cleared | 12/15/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 2/26/2025 | VASIL MIHALEV |
| Excavation more than 5-ft deep | Cleared | 3/19/2025 | CALOSHA APPROVED |
Contact Information
| Contractor | Coast Construction And Foundation Repair Inc; Lic. No.: 1007583-A | 302 FRASER LANE VENTURA, CA 93001 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Samara,, Muzahim Ali; Lic. No.: C26015 | 9100 S SEPULVEDA BLVD SUITE 115 LOS ANGELES, CA 90045 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 3/25/2025 | Corrections Issued | ALEXANDER HELFER |
| Pre-Inspection | 3/25/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Pre-Inspection | 6/17/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Piling/Pier/Caisson | 7/3/2025 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Concrete | 7/9/2025 | Conditional Approval | RAMAZANALI ALMASI |
| Piling/Pier/Caisson | 7/11/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 7/14/2025 | Approved | ROBERT PINA |
| Footing/Foundation/Slab | 7/18/2025 | Conditional Approval | ROBERT PINA |
| Deputy Reinf. Concrete | 7/21/2025 | Approved | ROBERT PINA |
| Deputy Shotcrete | 7/29/2025 | Approved | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Approved | ROBERT PINA |
| Deputy Shotcrete | 8/4/2025 | Approved | ROBERT PINA |
| Deputy Steel/Welding | 9/23/2025 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Steel/Welding | 9/24/2025 | Approved | ROBERT PINA |
| Deputy Reinf. Masonry | 10/22/2025 | Approved | ROBERT PINA |
| Deputy Reinf. Concrete | 10/27/2025 | Approved | ROBERT PINA |
| Deputy Reinf. Concrete | 10/29/2025 | Approved | ROBERT PINA |
| Deputy Shotcrete | 11/10/2025 | Corrections Issued | MICHAEL TEMPLE |
| Deputy Shotcrete | 11/12/2025 | Approved | ROBERT PINA |
| Deputy Shotcrete | 12/2/2025 | Approved | JONATHAN HOM |
| Deputy Shotcrete | 12/4/2025 | Approved | ROBERT PINA |
| Deputy Shotcrete | 12/11/2025 | Approved | ROBERT PINA |
| Final | 1/26/2026 | Permit Finaled | ROBERT PINA |