3411 N PASADENA AVE 90031
Certificate Information: 3411 N PASADENA AVE 90031
- Application / Permit
- 20020-10000-02233
- Plan Check / Job No.
- B20LA19774
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- EARLY START TEMPORARY SHORING FOR (N) MIXED USE BUILDING.
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Current Status
- Permit Finaled on 5/13/2024
Permit Application Status History
| Submitted | 11/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | KEVIN MORALES |
| Corrections Issued | 12/4/2020 | KEVIN MORALES |
| Quality Review Completed | 12/8/2020 | EUGENE BARBEAU |
| Plan Check Approved | 6/16/2022 | KEVIN MORALES |
| Issued | 6/16/2022 | APPLICANT |
| Permit Finaled | 5/10/2024 | JEFFREY FULTON |
Permit Application Clearance Information
| Highway dedication | Cleared | 2/1/2021 | ELAINE LEI |
| Miscellaneous | Cleared | 2/2/2021 | SAM NAVID |
| Miscellaneous | Cleared | 2/2/2021 | SAM NAVID |
| DAS Clearance | Cleared | 2/3/2021 | KEVIN MORALES |
| Green Code | Cleared | 2/3/2021 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2021 | ELAINE LEI |
| Low Impact Development | Cleared | 8/5/2021 | IDA MEISAMI-FARD |
| Hydrant and Access approval | Cleared | 8/20/2021 | ROBERT DUFF |
| Construction within easement | Cleared | 1/19/2022 | WALTER RAMIREZ |
| "D" conditions | Cleared | 4/4/2022 | LOUIS ORTEGA |
| "Q" conditions | Cleared | 4/4/2022 | LOUIS ORTEGA |
| "T" removal | Cleared | 4/4/2022 | LOUIS ORTEGA |
| Frnt yard landscape/Water mgmt | Cleared | 4/4/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 4/4/2022 | LOUIS ORTEGA |
| Opn space landscape/Water mgmt | Cleared | 4/4/2022 | LOUIS ORTEGA |
| Specific Plan | Cleared | 4/4/2022 | LOUIS ORTEGA |
| Specific Plan | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| ZA Case | Cleared | 4/4/2022 | LOUIS ORTEGA |
| Fire Marshall Fire Life Safety | Cleared | 4/20/2022 | ANDREW KO |
| Metro Rail approval | Cleared | 4/22/2022 | KEVIN MORALES |
| "D" conditions | Cleared | 5/4/2022 | MARITZA PRZEKOP |
| Work Adjacent to Public Way | Cleared | 5/11/2022 | ARMEN SARKISIAN |
| Encroachment in public way | Cleared | 5/20/2022 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2022 | ABEL CASILLAS |
| "Q" conditions | Cleared | 6/16/2022 | MARITZA PRZEKOP |
| "T" removal | Cleared | 6/16/2022 | MARITZA PRZEKOP |
| Metro Rail approval | Cleared | 6/16/2022 | MTA APPROVED |
Contact Information
| Contractor | Bernards Builders Inc; Lic. No.: 977134-B | 555 FIRST ST SAN FERNANDO, CA 91340 |
| Engineer | Choi,, Michael; Lic. No.: C67851 | 1221 N ORANGE DR 217 LOS ANGELES, CA 90038 |
| Engineer | Mahjoub,, Nina Azadeh; Lic. No.: C78947 | 21400 BURBANK BLVD 114 WOODLAND HILLS, CA 91367 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 8/15/2022 | Conditional Approval | MARK FERRARI |
| Pre-Inspection | 8/15/2022 | Partial Inspection | MARK FERRARI |
| Deputy Grading | 8/16/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 8/17/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 8/18/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 8/19/2022 | Conditional Approval | RAFAEL ESPINOZA |
| Piling/Pier/Caisson | 8/19/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Deputy Grading | 8/22/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/23/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/24/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/25/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Grading | 8/26/2022 | Conditional Approval | MARK FERRARI |
| Piling/Pier/Caisson | 8/26/2022 | Partial Inspection | MARK FERRARI |
| Deputy Grading | 8/29/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 8/30/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 8/31/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/1/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Grading | 9/2/2022 | Conditional Approval | WINSTON DUNNING |
| Piling/Pier/Caisson | 9/6/2022 | Partial Approval | BRUCE CAMPBELL |
| Deputy Grading | 9/8/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Grading | 9/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 10/3/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 10/5/2022 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/5/2022 | Partial Approval | MARK FERRARI |
| Deputy Grading | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 10/14/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Shotcrete | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Shotcrete | 11/2/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Shotcrete | 11/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 11/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 11/10/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 11/15/2022 | Partial Inspection | MARK FERRARI |
| Deputy Grading | 12/15/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 12/16/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/27/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 2/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 2/14/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Shotcrete | 2/15/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Deputy Reinf. Concrete | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 8/4/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 9/5/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 10/18/2023 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/19/2023 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 10/20/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 10/23/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 10/25/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 10/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 10/27/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 10/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 10/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/1/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 11/2/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Reinf. Concrete | 11/3/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 11/3/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 11/6/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/8/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/9/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 11/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/15/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 11/16/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 11/17/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 12/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 12/12/2023 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 12/15/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 1/9/2024 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 1/18/2024 | No Access for Inspection | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 1/19/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 1/23/2024 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 1/26/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 1/29/2024 | Conditional Approval | JACOB MYERS |
| Deputy Steel/Welding | 1/30/2024 | Conditional Approval | LARRY ARNICK |
| Deputy Steel/Welding | 2/23/2024 | Partial Approval | JACOB MYERS |
| Deputy Fireproofing | 2/27/2024 | Conditional Approval | LARRY ARNICK |
| Deputy Fireproofing | 2/29/2024 | Conditional Approval | LARRY ARNICK |
| Final | 5/10/2024 | Permit Finaled | JEFFREY FULTON |