21322 W OXNARD ST 91367
Certificate Information: 21322 W OXNARD ST 91367
- Application / Permit
- 20020-10000-02196
- Plan Check / Job No.
- B20LA19427
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Fence Wall
- Work Description
- (N) fence wall for 10'x17'4" trash enclosure.
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/8/2022
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | MICHAEL LOPEZ |
| Disabled Access Plans Picked Up | 11/5/2020 | APPLICANT |
| Corrections Issued | 11/12/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 11/21/2020 | PRANITA SHAH |
| Building Plans Picked Up | 12/23/2020 | APPLICANT |
| Applicant returned to address corrections | 3/16/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/1/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/18/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/16/2021 | TU HUA |
| Plan Check Approved | 8/13/2021 | CHRISTOPHER KOMANCHECK |
| Issued | 8/13/2021 | APPLICANT |
| Permit Finaled | 3/8/2022 | ANDREW DORSO |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/8/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 12/8/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 12/8/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 12/8/2020 | RICHARD REASER |
| DAS Clearance | Cleared | 2/8/2021 | SHINE LIN |
| Specific Plan | Cleared | 2/9/2021 | KRISTINE JEGALIAN |
Contact Information
| Architect | Valerio,, Niccolo; Lic. No.: C24228 | 5858 WILSHIRE BLVD # 203 LOS ANGELES, CA 90036 |
| Contractor | Padelford A J & Son Inc; Lic. No.: 222840-B | P O BOX 185 ARTESIA, CA 907020185 |
| Engineer | Momeni,, Moe; Lic. No.: C56774 | 8772 RAINBOW RIDGE LAS VEGAS, NV 89117 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2021 | Approved | DANIEL VARNUM |
| Masonry Wall/Backfill | 12/13/2021 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 2/10/2022 | Approved | DANIEL VARNUM |
| Deputy Reinf. Concrete | 3/2/2022 | Conditional Approval | DANIEL VARNUM |
| Final | 3/2/2022 | Corrections Issued | ANDREW DORSO |
| Final | 3/8/2022 | Permit Finaled | ANDREW DORSO |