13716 W VICTORY BLVD 91401

Certificate Information: 13716 W VICTORY BLVD 91401

Application / Permit
20020-10000-01960
Plan Check / Job No.
B20LA17068
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Shoring (Temporary)
Work Description
SHORING 2 OF 2
Permit Issued
Issued on 3/30/2022
Issuing Office
Current Status
Issued on 3/30/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/17/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 EUGENE BARBEAU
Disabled Access Plans Picked Up 10/19/2020 APPLICANT
Corrections Issued 10/30/2020 EUGENE BARBEAU
Quality Review Completed 11/5/2020 ALLEN MANALANSAN
Applicant returned to address corrections 3/23/2021 EUGENE BARBEAU
Green Plans Picked Up 3/23/2021 APPLICANT
Plan Check Approved 3/29/2022 EUGENE BARBEAU
Issued 3/30/2022 APPLICANT
Building Plans Picked Up 4/4/2022 APPLICANT

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 1/27/2022 CALOSHA APPROVED
Eng Process Fee Ord 176,300 Cleared 2/2/2022 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 2/2/2022 LEE GUILBEAUX

Contact Information

Contractor Ap Contractor; Lic. No.: 643672-B 10242 MONACO DRIVE      RANCHO CUCAMONGA, CA 91737
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2022 Partial Inspection CAMERON CHABAN
Deputy Grading 4/14/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/14/2022 Conditional Approval CAMERON CHABAN
Deputy Grading 4/15/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/15/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/21/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/25/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/2/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 5/3/2022 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 5/12/2022 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 7/11/2022 Not Ready for Inspection CAMERON CHABAN
Piling/Pier/Caisson 7/11/2022 Not Ready for Inspection CAMERON CHABAN
Deputy Reinf. Concrete 7/19/2022 Conditional Approval CAMERON CHABAN
Piling/Pier/Caisson 8/5/2022 Partial Inspection CAMERON CHABAN
Final 12/27/2022 Not Ready for Inspection ANDREW DORSO
Special/Order Compliance 12/27/2022 Not Ready for Inspection BRIAN KELLY
Piling/Pier/Caisson 5/11/2023 Partial Inspection CAMERON CHABAN
Special/Order Compliance 5/11/2023 Not Ready for Inspection STEVEN LEVITT