401 E 6TH ST 90014

Certificate Information: 401 E 6TH ST 90014

Application / Permit
20020-10000-01917
Plan Check / Job No.
B20LA16655
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
SHORING FOR A new 6 story 94 UNIT type III-A affordable apartments over 1 story of type I-A commercial, residential amenities, garage and back of house spaces. No basement. Project is 100% affordable.
Permit Issued
Issued on 9/10/2021
Issuing Office
Current Status
Permit Finaled on 5/23/2023

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 QUAN NGHIEM
Disabled Access Plans Picked Up 1/5/2021 APPLICANT
Corrections Issued 1/22/2021 QUAN NGHIEM
Quality Review Completed 1/22/2021 ALLEN MANALANSAN
Building Plans Picked Up 1/28/2021 APPLICANT
Applicant returned to address corrections 4/1/2021 QUAN NGHIEM
Applicant returned to address corrections 4/6/2021 QUAN NGHIEM
Applicant returned to address corrections 4/7/2021 QUAN NGHIEM
Applicant returned to address corrections 6/18/2021 QUAN NGHIEM
Green Plans Picked Up 6/29/2021 APPLICANT
Plan Check Approved 7/28/2021 QUAN NGHIEM
Issued 9/10/2021 APPLICANT
Permit Finaled 5/22/2023 NICK DANERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/23/2021 THOMAS LANG
Work Adjacent to Public Way Cleared 6/10/2021 JOSE RODRIGUEZ
Hold Cleared 10/20/2021 JASON SHEETS

Contact Information

Architect Olsen,, Eric H; Lic. No.: C27721 3802 OSTROM AVE      LONG BEACH, CA 90808
Contractor Suffolk Construction Company Inc; Lic. No.: 751099-B 525 MARKET STREET   SUITE 2850    SAN FRANCISCO, CA 94105
Engineer Aden,, Mark D; Lic. No.: S4779 1314 S GRAND BLVD 2-359      SPOKANE, WA 99202

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 11/16/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/17/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/18/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/19/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/22/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/23/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/24/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 11/30/2021 Conditional Approval NICK DANERI
Deputy Grading 12/1/2021 Conditional Approval NICK DANERI
Deputy Grading 12/2/2021 Conditional Approval NICK DANERI
Deputy Grading 12/3/2021 Conditional Approval NICK DANERI
Deputy Grading 12/6/2021 Conditional Approval NICK DANERI
Deputy Other (see comments) 12/8/2021 Conditional Approval NICK DANERI
Deputy Grading 12/17/2021 Conditional Approval NICK DANERI
Deputy Grading 12/20/2021 Conditional Approval NICK DANERI
Deputy Grading 12/21/2021 Conditional Approval NICK DANERI
Deputy Grading 12/22/2021 Conditional Approval NICK DANERI
Deputy Grading 1/3/2022 Partial Approval JAMES POWERS
Deputy Grading 1/4/2022 Conditional Approval RAFAEL ESPINOZA
Pre-Inspection 1/27/2022 Partial Approval NICK DANERI
Piling/Pier/Caisson 1/31/2022 Partial Approval NICK DANERI
Final 5/22/2023 Permit Finaled NICK DANERI