9900 W VENICE BLVD 90232
Certificate Information: 9900 W VENICE BLVD 90232
- Application / Permit
- 20020-10000-01574
- Plan Check / Job No.
- B20LA13287
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- TEMPORARY SHORING <<TIE BACK ANCHOR & CANTILEVER TYPE>> <REF.20030-10000-03919 & 20010-10000--02526>
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/16/2026
Permit Application Status History
| Submitted | 7/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | HERNAN ARREOLA |
| Corrections Issued | 8/27/2020 | DEAN LEE |
| Quality Review Completed | 8/31/2020 | ALLEN MANALANSAN |
| Disabled Access Plans Picked Up | 9/3/2020 | APPLICANT |
| Applicant returned to address corrections | 11/12/2020 | DEAN LEE |
| Applicant returned to address corrections | 11/17/2020 | DEAN LEE |
| Applicant returned to address corrections | 11/25/2020 | DEAN LEE |
| Applicant returned to address corrections | 12/9/2020 | DEAN LEE |
| Applicant returned to address corrections | 12/17/2020 | DEAN LEE |
| Applicant returned to address corrections | 12/29/2020 | DEAN LEE |
| Applicant returned to address corrections | 1/7/2021 | DEAN LEE |
| Applicant returned to address corrections | 1/14/2021 | DEAN LEE |
| Applicant returned to address corrections | 1/20/2021 | DEAN LEE |
| Applicant returned to address corrections | 2/17/2021 | DEAN LEE |
| Applicant returned to address corrections | 3/3/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/4/2021 | HERNAN ARREOLA |
| Green Plans Picked Up | 5/4/2021 | APPLICANT |
| Plan Check Approved | 7/22/2021 | HERNAN ARREOLA |
| Issued | 10/28/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
| Permit Finaled | 1/14/2026 | DERRICK SPENCER |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | ANTHONY MAINEZ |
| Excavation more than 5-ft deep | Cleared | 2/24/2021 | CALOSHA APPROVED |
| Permit | Cleared | 3/19/2021 | NIKTA MOUSAVI |
| Work Adjacent to Public Way | Cleared | 4/12/2021 | SAUL GARCIA |
Contact Information
| Contractor | Fassberg Construction Company; Lic. No.: 470049-B | 17000 VENTURA BLVD #200 ENCINO, CA 91316 |
| Engineer | Derkalousdian,, Hrair Harry; Lic. No.: C79694 | 3622 VIRGINIA STREET GLENDALE, CA 91214 |
| Engineer | Young,, Don Yuk-Man; Lic. No.: C35713 | 149 PASADENA AVE STE B SOUTH PASADENA, CA 91030 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 1/7/2022 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 1/10/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/11/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/12/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/13/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 1/14/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/18/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/19/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/20/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 1/21/2022 | Approved | NICK LAROCCA |
| Deputy Wood Construction | 2/22/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 2/24/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 2/28/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/1/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/1/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/2/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/2/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/3/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/3/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/4/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/4/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/7/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/7/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/8/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/9/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/10/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/14/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/15/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/16/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/17/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/18/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/21/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 3/21/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/22/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 3/22/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/30/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 3/31/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 4/1/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 4/7/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 4/8/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 4/11/2022 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/9/2022 | Conditional Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 12/2/2022 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 12/2/2022 | Approved | DERRICK SPENCER |
| Deputy Grading | 1/5/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/20/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/22/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/25/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/26/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/27/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/28/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/4/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 5/4/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 5/8/2023 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 5/12/2023 | Conditional Approval | HENRY BAGHDASSARIAN |
| Deputy Reinf. Masonry | 5/19/2023 | Approved | DERRICK SPENCER |
| Deputy Wood Construction | 10/3/2023 | Conditional Approval | DERRICK SPENCER |
| Final | 3/27/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 3/27/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Rough | 4/2/2024 | Approved | DERRICK SPENCER |
| Final | 6/26/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 6/26/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 1/14/2026 | Permit Finaled | DERRICK SPENCER |
| Green Building Final | 1/14/2026 | Approved | DERRICK SPENCER |