26900 S WESTERN AVE 90732
Certificate Information: 26900 S WESTERN AVE 90732
- Application / Permit
- 20020-10000-01326
- Plan Check / Job No.
- G20LA00126
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL FOR TRACT VTT 71886-06. FOR GRDING PERMIT SEE PERMIT 20030-10000-03145. 2 of 2
- Permit Issued
- Issued on 12/28/2020
- Issuing Office
- Current Status
- Issued on 12/28/2020
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2020 | DAN RYAN EVANGELISTA |
| Corrections Issued | 7/13/2020 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 12/28/2020 | DAN RYAN EVANGELISTA |
| Issued | 12/28/2020 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/13/2020 | JONATHAN HOM |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2020 | HISASHI KOBAYAKAWA |
| Landscape for retaining wall | Cleared | 12/15/2020 | JASON CHAN |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | TAO YANG |
| Specific Plan | Cleared | 12/15/2020 | JASON CHAN |
| Tract Map conditions | Cleared | 12/15/2020 | JASON CHAN |
| Excavation more than 5-ft deep | Cleared | 12/28/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | Design Masonry Inc; Lic. No.: 941944-B | 20703 SANTA CLARA ST CANYON COUNTRY, CA 91351 |
| Engineer | Reed,, Ronald Albert; Lic. No.: GE2524 | 3186 AIRWAY AVE K COSTA MESA, CA 92626 |
| Geologist | Wolfe,, Theodore Marshall; Lic. No.: EG1626 | 18610 CABALLERO CT TARZANA, CA 91356 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/5/2021 | No Access for Inspection | JOHN KLARIN |
| Reinforced Masonry Frame | 1/7/2021 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 1/9/2021 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 1/12/2021 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/12/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/13/2021 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/14/2021 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/15/2021 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/16/2021 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/20/2021 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 1/21/2021 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 9/29/2021 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 10/3/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 10/3/2021 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/3/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 10/3/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 10/5/2021 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 10/6/2021 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 10/7/2021 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 10/7/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 10/8/2021 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/27/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/29/2022 | Approved | JOEY BUCHANAN |
| Reinforced Concrete Frame | 5/5/2022 | Partial Approval | JOEY BUCHANAN |
| Reinforced Masonry Frame | 5/24/2022 | Not Ready for Inspection | DAVID TSAU |
| Reinforced Masonry Frame | 5/25/2022 | Approved | JOEY BUCHANAN |