600 N CASCADA WAY 90049

Certificate Information: 600 N CASCADA WAY 90049

Application / Permit
20020-10000-01231
Plan Check / Job No.
B20LA10136
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(26) Temporary Structure
Work Description
TEMPORARY SHORING FOR NEW 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT AND ATTACHED GARAGE AND SITE RETAINING WALL
Permit Issued
Issued on 11/15/2021
Issuing Office
Current Status
Issued on 11/15/2021

Permit Application Status History

Submitted 6/10/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 STARR CHEN
Corrections Issued 7/17/2020 STARR CHEN
Quality Review Completed 7/31/2020 HERNAN ARREOLA
Building Plans Picked Up 8/5/2020 APPLICANT
Applicant returned to address corrections 11/17/2020 STARR CHEN
Applicant returned to address corrections 5/14/2021 STARR CHEN
Applicant returned to address corrections 5/19/2021 STARR CHEN
Applicant returned to address corrections 10/29/2021 STARR CHEN
Plan Check Approved 11/15/2021 STARR CHEN
Issued 11/15/2021 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Rubio,, Edgardo A; Lic. No.: C26444 970 JUNIPERO DRIVE      COSTA MESA, CA 92626
Contractor Roth Development Group Inc; Lic. No.: 1006385-B 602 ROSARIO DR      THOUSAND OAKS, CA 91362
Engineer Jung,, Jason Stanley; Lic. No.: C80569 1032 S PALM AVE      SAN GABRIEL, CA 91776
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406
Engineer Miyamoto,, Yoshiaki Wayne; Lic. No.: L4825 4396 MENTONE AVE      CULVER CITY, CA 90230

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/22/2022 Not Ready for Inspection JONATHAN HOM
Excavation/Setback/Form/Re-Bar 6/23/2022 Corrections Issued TIMOTHY POWELL
Piling/Pier/Caisson 6/23/2022 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 6/28/2022 Partial Inspection TIMOTHY POWELL
Piling/Pier/Caisson 6/28/2022 Partial Inspection TIMOTHY POWELL
Deputy Steel/Welding 9/1/2022 Partial Approval CHARLES POWELL
Deputy Steel/Welding 9/6/2022 Conditional Approval MICHAEL TEMPLE
Deputy Reinf. Concrete 9/26/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 10/13/2022 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 1/25/2024 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 1/25/2024 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 1/26/2024 Approved ROBERT PINA
Piling/Pier/Caisson 1/26/2024 Partial Inspection RUSSELL BONVOULOIR
Deputy Reinf. Concrete 1/29/2024 Approved ALEXANDER HELFER