1027 N RAVOLI DR 90272
Certificate Information: 1027 N RAVOLI DR 90272
- Application / Permit
- 20020-10000-01107
- Plan Check / Job No.
- B20LA09294
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW 6' MAX HEIGHT RETAINING WALL, APPROX 75' LENGTH MINOR EXTERIOR REMODEL INCLUDING STAIRS ON GRADE, GARDEN WALL AND NEW 6' MAX HEIGHT PEDESTRAIN GATE
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/19/2021
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | TSE MING HUANG |
| Corrections Issued | 6/1/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 10/5/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 10/27/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 10/29/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 11/2/2020 | APPLICANT |
| Issued | 12/8/2020 | APPLICANT |
| Permit Finaled | 7/16/2021 | MATTHEW JENKINS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/5/2020 | MARITZA PRZEKOP |
| ZA Case | Cleared | 6/5/2020 | MARITZA PRZEKOP |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 8/3/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/3/2020 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 10/29/2020 | TSE MING HUANG |
| Grading Pre-Inspection | Cleared | 10/29/2020 | TSE MING HUANG |
Contact Information
| Contractor | Hart Built Construction Inc; Lic. No.: 840797-B | 16683 CHARMEL LANE PACIFIC PALISADES, CA 90272 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| RUSSELL BONVOULOIR, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2020 | Corrections Issued | BRIAN OLSON |
| Excavation/Setback/Form/Re-Bar | 12/17/2020 | Not Ready for Inspection | BRIAN OLSON |
| Excavation/Setback/Form/Re-Bar | 12/29/2020 | Conditional Approval | BRIAN OLSON |
| Excavation/Setback/Form/Re-Bar | 1/20/2021 | Partial Inspection | MATTHEW JENKINS |
| Footing/Foundation/Slab | 1/20/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Masonry Wall/Backfill | 1/20/2021 | Partial Inspection | MATTHEW JENKINS |
| Special/Order Compliance | 1/22/2021 | Partial Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 1/26/2021 | Partial Approval | BRIAN OLSON |
| Masonry Wall/Backfill | 1/26/2021 | Partial Approval | BRIAN OLSON |
| Masonry Wall/Backfill | 1/28/2021 | Partial Approval | BRIAN OLSON |
| Excavation/Setback/Form/Re-Bar | 2/2/2021 | Not Ready for Inspection | KIRK LINKLATER |
| Excavation/Setback/Form/Re-Bar | 2/5/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 2/9/2021 | Corrections Issued | MATTHEW JENKINS |
| Footing/Foundation/Slab | 2/10/2021 | Corrections Issued | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 2/12/2021 | Partial Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 2/24/2021 | Partial Inspection | MATTHEW JENKINS |
| Final | 2/25/2021 | Corrections Issued | KIRK LINKLATER |
| Excavation/Setback/Form/Re-Bar | 3/9/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Pre-Inspection | 4/1/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 4/14/2021 | Partial Approval | BRIAN OLSON |
| Excavation/Setback/Form/Re-Bar | 4/28/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Conditional Approval | MATTHEW JENKINS |
| Final | 5/14/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 5/18/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 6/16/2021 | Partial Inspection | MATTHEW JENKINS |
| Pre-Inspection | 6/25/2021 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 7/16/2021 | Permit Finaled | MATTHEW JENKINS |