5600 N SEPULVEDA BLVD 91411

Certificate Information: 5600 N SEPULVEDA BLVD 91411

Application / Permit
20020-10000-01104
Plan Check / Job No.
B20LA09269
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
REMOVE AND REPLACE UNDERGROUND GASOLINE TANKS. REMOVE AND REPLACE 4 FUEL DISPENSERS. PROVIDE SHORING FOR TANK REMOVAL AND INSTALLATION
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO in Progress on 1/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/17/2020 ERIC WONG
Corrections Issued 6/24/2020 ERIC WONG
Quality Review Completed 6/24/2020 KEN GILL
Applicant returned to address corrections 10/29/2020 ERIC WONG
Plan Check Approved 12/22/2021 ERIC WONG
Issued 1/14/2022 APPLICANT
Building Plans Picked Up 1/20/2022 APPLICANT
CofO in Progress 1/6/2023 BRIAN KELLY

Permit Application Clearance Information

Address approval Cleared 7/30/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/30/2020 LEE GUILBEAUX
Highway dedication Cleared 7/30/2020 LEE GUILBEAUX
Sewer availability Cleared 7/30/2020 LEE GUILBEAUX
Work Adjacent to Public Way Cleared 7/30/2020 LEE GUILBEAUX
CPC Cleared 8/5/2020 RICHARD REASER
CPC Cleared 8/5/2020 RICHARD REASER
ZA Case Cleared 8/5/2020 RICHARD REASER
ZI Cleared 8/5/2020 RICHARD REASER
Underground fuel tank Cleared 11/6/2020 GREGORY STEVENS
Gasoline station Cleared 11/18/2020 SCAQMD APPROVED
Low Impact Development Cleared 12/22/2021 AMMAR ELTAWIL

Contact Information

Architect Pedro,, Roy W; Lic. No.: C28504 6930 DESTINY DRIVE # 100      ROCKLIN, CA 95677
Contractor Perry Wayne Inc; Lic. No.: 300345-B 8281 COMMONWEALTH AVE      BUENA PARK, CA 90621
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801
Geologist Haney,, Harry Drew; Lic. No.: EG2091 8860 CORBIN AVE #341      CANOGA PARK, CA 91324

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/22/2022 Partial Inspection DANIEL VARNUM
Deputy Steel/Welding 9/13/2022 Conditional Approval DANIEL VARNUM
Deputy Grading 9/15/2022 Conditional Approval ANDREW DORSO
Piling/Pier/Caisson 10/24/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 10/27/2022 Approved JOHN KITCKO
Footing/Foundation/Slab 11/10/2022 Partial Approval CAMERON CHABAN
Final 12/14/2022 OK to Issue CofO BRIAN KELLY