1417 N FERMO DR 90272
Certificate Information: 1417 N FERMO DR 90272
- Application / Permit
- 20020-10000-01041
- Plan Check / Job No.
- B20LA08598
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (61) Tennis Court
- Work Description
- (N) SPORTS COURT 5 OF 7
- Permit Issued
- Issued on 10/28/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/12/2025
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 6/25/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/20/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/21/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 7/30/2020 | APPLICANT |
| Green Plans Picked Up | 9/25/2020 | APPLICANT |
| Applicant returned to address corrections | 10/15/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 10/19/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 10/26/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/27/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/26/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 3/3/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 4/19/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 4/22/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 5/6/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 6/10/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/19/2021 | ARSALAN SHABESTARI |
| Issued | 10/28/2021 | APPLICANT |
| CofO in Progress | 3/4/2025 | KEVIN SARGSYAN |
| CofO in Progress | 3/7/2025 | VASIL MIHALEV |
| CofO in Progress | 3/7/2025 | VASIL MIHALEV |
| Permit Finaled | 3/12/2025 | KENNETH NAGLE |
| No Progress | 3/12/2025 | KENNETH NAGLE |
| CofO in Progress | 3/12/2025 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2020 | RAYMOND MUGAMBWA |
| Hydrant and Access approval | Cleared | 6/25/2021 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 6/28/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 6/28/2021 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 8/5/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 8/5/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 8/5/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 8/5/2021 | RAYMOND MUGAMBWA |
| BHO/Hillside ordinance | Cleared | 8/5/2021 | RAYMOND MUGAMBWA |
| ZA Case | Cleared | 8/13/2021 | RUBEN VASQUEZ |
| Excavation more than 5-ft deep | Cleared | 10/19/2021 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 10/19/2021 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 10/19/2021 | ARSALAN SHABESTARI |
| Green Code | Cleared | 10/19/2021 | ARSALAN SHABESTARI |
Contact Information
| Architect | Backen,, Howard John; Lic. No.: C4978 | 2352 MARINSHIP WAY SAUSALITO, CA 94965 |
| Contractor | Ceci Clarke Inc; Lic. No.: 1040135-B | 444 ARNEILL ROAD CAMARILLO, CA 93010 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2024 | No Access for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/20/2024 | Approved | ARAM AVEDISIAN |
| Final | 3/4/2025 | Conditional Approval | KEVIN SARGSYAN |
| Final | 3/12/2025 | Permit Finaled | KENNETH NAGLE |