863 N HYPERION AVE 90029
Certificate Information: 863 N HYPERION AVE 90029
- Application / Permit
- 20020-10000-00994
- Plan Check / Job No.
- B20LA06065
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- site retaining wall - retaining from 2'-6" up to 6' ht. along p.l. ( max retaining wall height including railing on top of wall is 6' ht. measuring from natural grade)
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/26/2023
Permit Application Status History
| Submitted | 4/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2020 | SAM CHANG |
| Corrections Issued | 5/5/2020 | SAM CHANG |
| Quality Review Completed | 5/20/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 6/11/2020 | APPLICANT |
| Applicant returned to address corrections | 9/23/2020 | SAM CHANG |
| Applicant returned to address corrections | 10/20/2020 | SAM CHANG |
| Green Plans Picked Up | 12/3/2020 | APPLICANT |
| Applicant returned to address corrections | 12/17/2020 | SAM CHANG |
| Applicant returned to address corrections | 3/1/2021 | SAM CHANG |
| Plan Check Approved | 3/25/2021 | SAM CHANG |
| Issued | 3/26/2021 | APPLICANT |
| Permit Finaled | 12/22/2023 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Excavation more than 5-ft deep | Cleared | 9/4/2020 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 2/8/2021 | TERRI OSBORNE |
| Grading Pre-Inspection | Cleared | 2/9/2021 | SAM CHANG |
Contact Information
| Architect | Gibbs,, Kurt Robert; Lic. No.: C22275 | 3575 LONG BEACH BLVD LONG BEACH, CA 90807 |
| Contractor | Owner-Builder | , |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/6/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Pre-Inspection | 4/20/2021 | Partial Approval | ROBERT HUGHES |
| Piling/Pier/Caisson | 4/28/2021 | Not Ready for Inspection | ROBERT HUGHES |
| Footing/Foundation/Slab | 5/24/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Concrete | 6/8/2021 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 6/8/2021 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Masonry | 6/14/2021 | Approved | ROBERT HUGHES |
| Footing/Foundation/Slab | 6/16/2021 | Partial Approval | ROBERT HUGHES |
| Deputy Reinf. Masonry | 6/25/2021 | Approved | ROBERT HUGHES |
| Masonry Wall/Backfill | 7/6/2021 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 11/12/2021 | Approved | ALEXANDER HELFER |
| Deputy Steel/Welding | 11/15/2021 | Approved | ROBERT HUGHES |
| Masonry Wall/Backfill | 12/22/2021 | Partial Approval | ROBERT HUGHES |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Partial Approval | ROBERT HUGHES |
| Footing/Foundation/Slab | 9/8/2022 | Partial Approval | ROBERT HUGHES |
| Masonry Wall/Backfill | 9/19/2022 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Masonry | 9/20/2022 | Approved | ROBERT HUGHES |
| Final | 12/22/2023 | Permit Finaled | RUSSELL BONVOULOIR |