20539 W VENTURA BLVD 91364
Certificate Information: 20539 W VENTURA BLVD 91364
- Application / Permit
- 20020-10000-00913
- Plan Check / Job No.
- B20LA07529
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- TEMPORARY SHORING (7,300 SF / MAX. 20 FT DEPTH) FOR A NEW AUTOMOBILE DEALERSHIP ASSOC. W/LADBS PERMIT APPLICATION NO. 20010-10000-00457
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/20/2021
Permit Application Status History
| Submitted | 4/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | HERNAN ARREOLA |
| Corrections Issued | 6/1/2020 | HERNAN ARREOLA |
| Quality Review Completed | 6/3/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 7/17/2020 | APPLICANT |
| Plan Check Approved | 10/2/2020 | HERNAN ARREOLA |
| Issued | 10/2/2020 | APPLICANT |
| Permit Finaled | 8/20/2021 | CAMERON CHABAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/28/2020 | RICHARD REASER |
| "T" removal | Cleared | 7/28/2020 | RICHARD REASER |
| CPC | Cleared | 7/28/2020 | RICHARD REASER |
| Specific Plan | Cleared | 7/28/2020 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 9/2/2020 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 9/2/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Pacific West Builders Inc; Lic. No.: 752705-B | 1197 LOS ANGELES AVE STE C 166 SIMI VALLEY, CA 93065 |
| Engineer | Salter,, David R; Lic. No.: C69911 | 3445 CEDAR ST SANTA YNEZ, CA 93460 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 10/22/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Grading | 10/23/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Grading | 10/26/2020 | Approved | ROBERT DAVIS |
| Deputy Grading | 10/27/2020 | Conditional Approval | ANDREW DORSO |
| Deputy Grading | 10/28/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 10/28/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Grading | 10/29/2020 | Approved | ROBERT DAVIS |
| Deputy Steel/Welding | 10/29/2020 | Approved | ROBERT DAVIS |
| Deputy Grading | 10/30/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Grading | 11/2/2020 | No Result Entered | GARY EWELL |
| Deputy Grading | 11/4/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Grading | 11/5/2020 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 11/6/2020 | Approved | HAMID PISHEHVAR |
| Deputy Grading | 11/9/2020 | Approved | JEFFREY DURAN |
| Deputy Grading | 11/10/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 11/10/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Grading | 11/12/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 11/12/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Grading | 11/13/2020 | Approved | HAMID PISHEHVAR |
| Deputy Reinf. Concrete | 11/13/2020 | Approved | HAMID PISHEHVAR |
| Deputy Grading | 11/25/2020 | Conditional Approval | DANIEL VARNUM |
| Deputy Grading | 11/30/2020 | No Result Entered | GARY EWELL |
| Deputy Grading | 12/7/2020 | Conditional Approval | JEFFREY DURAN |
| Final | 8/20/2021 | Permit Finaled | CAMERON CHABAN |