5333 W ZOO DR 90027
Certificate Information: 5333 W ZOO DR 90027
- Application / Permit
- 20020-10000-00785
- Plan Check / Job No.
- B20LA05694
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- PROPOSED RETAINING WALL FOR NEW CAPE VULTURE EXHIBIT. 2 OF 4.
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | LAMAR DAVIS |
| Corrections Issued | 4/9/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 5/5/2020 | QUAN NGHIEM |
| Disabled Access Plans Picked Up | 5/5/2020 | APPLICANT |
| Applicant returned to address corrections | 8/25/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/15/2020 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/16/2020 | MICHAEL LOPEZ |
| Green Plans Picked Up | 10/19/2020 | APPLICANT |
| Applicant returned to address corrections | 2/17/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 4/8/2021 | MICHAEL LOPEZ |
| Building Plans Picked Up | 4/15/2021 | APPLICANT |
| Applicant returned to address corrections | 6/16/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/24/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/20/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 3/24/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 5/10/2022 | MICHAEL LOPEZ |
| Issued | 1/23/2023 | APPLICANT |
| Permit Finaled-Status Void | 11/12/2024 | DAVID BURKHEAD |
| Permit Finaled | 11/12/2024 | DAVID BURKHEAD |
| Re-Activate Permit | 11/14/2024 | DAVID BURKHEAD |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 9/21/2020 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 9/21/2020 | LAMBERT GIESSINGER |
| Landscape for retaining wall | Cleared | 10/2/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 10/2/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 10/2/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 10/2/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 10/2/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 10/2/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 10/2/2020 | ANACANY HURTADO |
| Grading Pre-Inspection | Cleared | 1/26/2021 | ALEXANDER HELFER |
Contact Information
| Architect | Torre,, Leonard Azeo; Lic. No.: C23147 | 5005 MAGAZINE STREET NEW ORLEANS, LA 70115 |
| Contractor | Houalla Enterprises Ltd; Lic. No.: 597589-B | 2610 AVON ST NEWPORT BEACH, CA 92663 |
| Engineer | Fredericks,, Douglas Martin; Lic. No.: C50863 | 1075 CREEKSIDE RIDGE DRIVE 200 ROSEVILLE, CA 95678 |
| Engineer | Miscione,, Frank Vincent; Lic. No.: C69031 | 30014 LEXINGTON VAL VERDE, CA 91384 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2023 | Approved | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 8/29/2023 | Partial Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 1/5/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/5/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Masonry | 1/5/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Shotcrete | 1/5/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 1/8/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 1/8/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Reinf. Masonry | 1/8/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Shotcrete | 1/8/2024 | Conditional Approval | DAVID BURKHEAD |
| Deputy Drilled-In Anchors | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Masonry | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Shotcrete | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 1/11/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 1/11/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Masonry | 1/11/2024 | Partial Approval | EDWIN GREGORYONA |
| Deputy Shotcrete | 1/11/2024 | Partial Approval | EDWIN GREGORYONA |
| Final | 8/5/2024 | Not Ready for Inspection | DAVID BURKHEAD |
| Final | 9/27/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 11/12/2024 | Permit Finaled | DAVID BURKHEAD |