2915 W AVENEL TER 90039

Certificate Information: 2915 W AVENEL TER 90039

Application / Permit
20020-10000-00733
Plan Check / Job No.
B20LA05016
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
site retaining wall from 1'-to 5' and block wall from 3'-6" front yard to 6' ht. side and rear yards
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
Permit Finaled on 5/10/2023

Permit Application Status History

Submitted 3/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 SAM CHANG
Corrections Issued 4/1/2020 SAM CHANG
Quality Review Completed 4/15/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 4/24/2020 APPLICANT
Applicant returned to address corrections 7/16/2020 SAM CHANG
Applicant returned to address corrections 8/7/2020 SAM CHANG
Green Plans Picked Up 8/28/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 SAM CHANG
Applicant returned to address corrections 10/27/2020 SAM CHANG
Applicant returned to address corrections 1/29/2021 SAM CHANG
Applicant returned to address corrections 2/25/2021 SAM CHANG
Applicant returned to address corrections 4/8/2021 SAM CHANG
Plan Check Approved 4/12/2021 SAM CHANG
Issued 4/20/2021 APPLICANT
Permit Finaled 5/9/2023 LANNY MERRICK

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Gibbs,, Kurt Robert; Lic. No.: C22275 3575 LONG BEACH BLVD      LONG BEACH, CA 90807
Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Geologist Hill,, Thomas George; Lic. No.: EG1100 3210 VAL VERDE      LONG BEACH, CA 90808

Inspector Information

LANNY MERRICK, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/13/2022 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 4/14/2022 Not Ready for Inspection SCOTT FINNILA
Masonry Wall/Backfill 4/20/2022 Partial Approval ROBERT HUGHES
Deputy Reinf. Concrete 4/21/2022 Approved ROBERT HUGHES
Masonry Wall/Backfill 4/21/2022 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 5/12/2022 Partial Approval ROBERT HUGHES
Masonry Wall/Backfill 5/25/2022 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 6/28/2022 Partial Approval ROBERT HUGHES
Special/Order Compliance 8/19/2022 Not Ready for Inspection ROBERT HUGHES
Final 5/9/2023 Permit Finaled LANNY MERRICK