20101 W VENTURA BLVD 91364
Certificate Information: 20101 W VENTURA BLVD 91364
- Application / Permit
- 20020-10000-00698
- Plan Check / Job No.
- B20LA05711
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Canopy
- Work Description
- Install 1 drive thru capony structure for supporting menuboard
- Permit Issued
- Issued on 6/29/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 4/1/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/5/2020 | RACHEL BEYENE |
| Plan Check Approved | 6/9/2020 | RAHEL BEYENE |
| Issued | 6/29/2020 | LADBS |
| Building Plans Picked Up | 6/30/2020 | APPLICANT |
| Permit Finaled | 4/13/2023 | BRIAN KELLY |
Permit Application Clearance Information
| "D" conditions | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| ZA Case | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| ZA Case | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| ZA Case | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| ZA Case | Cleared | 4/17/2020 | VINCENT QUITORIANO |
| Specific Plan | Cleared | 4/23/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 4/24/2020 | VINCENT QUITORIANO |
| Grading Pre-Inspection | Cleared | 5/14/2020 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/15/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | National Sign & Marketing Corporation; Lic. No.: 745030-B | 13580 5TH STREET CHINO, CA 91710 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/2/2020 | Approved | JEFFREY FULTON |
| Piling/Pier/Caisson | 7/2/2020 | Approved | JEFFREY FULTON |
| Final | 7/30/2020 | Not Ready for Inspection | ROBERT DAVIS |
| Reinforced Masonry Frame | 7/30/2020 | Approved | ROBERT DAVIS |
| Final | 10/16/2020 | Partial Inspection | DANIEL VARNUM |
| Final | 4/13/2023 | Permit Finaled | BRIAN KELLY |