20101 W VENTURA BLVD 91364

Certificate Information: 20101 W VENTURA BLVD 91364

Application / Permit
20020-10000-00698
Plan Check / Job No.
B20LA05711
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Canopy
Work Description
Install 1 drive thru capony structure for supporting menuboard
Permit Issued
Issued on 6/29/2020
Issuing Office
Metro
Current Status
Permit Finaled on 4/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/23/2020 FARSHAD ALIMOHAMADI
Corrections Issued 4/1/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/5/2020 RACHEL BEYENE
Plan Check Approved 6/9/2020 RAHEL BEYENE
Issued 6/29/2020 LADBS
Building Plans Picked Up 6/30/2020 APPLICANT
Permit Finaled 4/13/2023 BRIAN KELLY

Permit Application Clearance Information

"D" conditions Cleared 4/17/2020 VINCENT QUITORIANO
Miscellaneous Cleared 4/17/2020 VINCENT QUITORIANO
Miscellaneous Cleared 4/17/2020 VINCENT QUITORIANO
Miscellaneous Cleared 4/17/2020 VINCENT QUITORIANO
ZA Case Cleared 4/17/2020 VINCENT QUITORIANO
ZA Case Cleared 4/17/2020 VINCENT QUITORIANO
ZA Case Cleared 4/17/2020 VINCENT QUITORIANO
ZA Case Cleared 4/17/2020 VINCENT QUITORIANO
Specific Plan Cleared 4/23/2020 VINCENT QUITORIANO
Miscellaneous Cleared 4/24/2020 VINCENT QUITORIANO
Grading Pre-Inspection Cleared 5/14/2020 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 5/15/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 5/15/2020 ADRIAN CASTRO

Contact Information

Contractor National Sign & Marketing Corporation; Lic. No.: 745030-B 13580 5TH STREET      CHINO, CA 91710

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2020 Approved JEFFREY FULTON
Piling/Pier/Caisson 7/2/2020 Approved JEFFREY FULTON
Final 7/30/2020 Not Ready for Inspection ROBERT DAVIS
Reinforced Masonry Frame 7/30/2020 Approved ROBERT DAVIS
Final 10/16/2020 Partial Inspection DANIEL VARNUM
Final 4/13/2023 Permit Finaled BRIAN KELLY