4344 W WILLOW BROOK AVE 90029

Certificate Information: 4344 W WILLOW BROOK AVE 90029

Application / Permit
20020-10000-00625
Plan Check / Job No.
B20LA05291
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW PROPOSED 370' TOTAL LENGTH, 6'-0" MAX HEIGHT RETAINING WALL. 3'-6" MAX HEIGHT IN 10' FRONT YARD
Permit Issued
Issued on 5/20/2020
Issuing Office
Current Status
Permit Finaled on 1/6/2023

Permit Application Status History

Submitted 3/16/2020 APPLICANT
Assigned to Plan Check Engineer 3/20/2020 GEORGE ALVAREZ
Corrections Issued 3/26/2020 GEORGE ALVAREZ
Quality Review Completed 4/2/2020 STANLEY RAAP
Plan Check Approved 5/7/2020 GEORGE ALVAREZ
Issued 5/20/2020 APPLICANT
Building Plans Picked Up 5/26/2020 APPLICANT
Permit Finaled 1/6/2023 ROBERT HUGHES

Permit Application Clearance Information

GPI Written Notices Cleared 5/7/2020 GEORGE ALVAREZ
Grading Pre-Inspection Cleared 5/7/2020 GEORGE ALVAREZ

Contact Information

Contractor Stonewall Construction Inc; Lic. No.: 1014817-B P O BOX 103      SAN FERNANDO, CA 91340
Engineer Nazemi,, Hassan Steve; Lic. No.: C44100 275 CENTENNIAL WAY 205      TUSTIN, CA 92780
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 11/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
Special/Order Compliance 12/1/2021 Corrections Issued ALEJANDRO DE ARTOLA
Special/Order Compliance 12/8/2021 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/4/2022 Not Ready for Inspection ROBERT HUGHES
Footing/Foundation/Slab 4/6/2022 Approved ALEXANDER HELFER
Masonry Wall/Backfill 4/20/2022 Approved ROBERT HUGHES
Masonry Wall/Backfill 4/20/2022 Partial Approval ROBERT HUGHES
Masonry Wall/Backfill 4/28/2022 Partial Approval ROBERT HUGHES
Footing/Foundation/Slab 5/25/2022 Partial Approval ROBERT HUGHES
Masonry Wall/Backfill 6/2/2022 Partial Approval MATTHEW JENKINS
Masonry Wall/Backfill 7/6/2022 Partial Approval MATTHEW JENKINS
Final 11/10/2022 Not Ready for Inspection ROBERT HUGHES
Final 1/6/2023 Permit Finaled ROBERT HUGHES