20539 W VENTURA BLVD 91364
Certificate Information: 20539 W VENTURA BLVD 91364
- Application / Permit
- 20020-10000-00612
- Plan Check / Job No.
- B20LA05090
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- Early Start permit for : CONSTRUCTION OF SITE RETAINING WALLS. 9' MAX HEIGHT
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Current Status
- Permit Finaled on 11/26/2024
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | HERNAN ARREOLA |
| Corrections Issued | 4/9/2020 | HERNAN ARREOLA |
| Quality Review Completed | 4/17/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 4/17/2020 | APPLICANT |
| Applicant returned to address corrections | 7/23/2020 | HERNAN ARREOLA |
| Plan Check Approved | 10/2/2020 | HERNAN ARREOLA |
| Issued | 10/2/2020 | APPLICANT |
| Permit Finaled | 11/26/2024 | ROBERT DAVIS |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 7/28/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 7/28/2020 | RICHARD REASER |
| Specific Plan | Cleared | 7/28/2020 | RICHARD REASER |
Contact Information
| Contractor | Pacific West Builders Inc; Lic. No.: 752705-B | 1197 LOS ANGELES AVE STE C 166 SIMI VALLEY, CA 93065 |
| Engineer | Salter,, David R; Lic. No.: C69911 | 3445 CEDAR ST SANTA YNEZ, CA 93460 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 10/27/2020 | Approved | HAMID PISHEHVAR |
| Deputy Steel/Welding | 10/30/2020 | Conditional Approval | JEFFREY DURAN |
| Deputy Grading | 11/10/2020 | Conditional Approval | JEFFREY DURAN |
| Reinforced Masonry Frame | 6/25/2021 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 12/7/2021 | Conditional Approval | JEFFREY DURAN |
| Masonry Wall/Backfill | 12/8/2021 | Partial Approval | DANIEL VARNUM |
| Reinforced Concrete Frame | 1/24/2022 | Partial Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 6/10/2022 | Partial Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 6/22/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 6/22/2022 | Partial Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 6/23/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 6/28/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 7/11/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Reinf. Concrete | 8/11/2022 | No Result Entered | GARY EWELL |
| Deputy Reinf. Concrete | 8/25/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Reinf. Concrete | 12/15/2022 | Conditional Approval | DANIEL VARNUM |
| Final | 8/28/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Final | 9/21/2023 | Partial Inspection | KENNETH ROBERTS |
| Final | 11/26/2024 | Permit Finaled | ROBERT DAVIS |