20333 S NORMANDIE AVE 90501
Certificate Information: 20333 S NORMANDIE AVE 90501
- Application / Permit
- 20020-10000-00608
- Plan Check / Job No.
- B20LA05080
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL AROUND (27'-4" x 104'-4") ELECTRICAL EQUIPMENT FOR SOLAR FIT PROJECT; MAX 5'-3" HIGH
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- Permit Finaled on 7/19/2021
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/20/2020 | SINA KHOSRAVI |
| Corrections Issued | 3/24/2020 | SINA KHOSRAVI |
| Quality Review Completed | 4/1/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 5/22/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/29/2020 | SINA KHOSRAVI |
| Plan Check Approved | 7/1/2020 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
| Issued | 8/17/2020 | APPLICANT |
| Permit Finaled | 7/19/2021 | JOEY BUCHANAN |
Permit Application Clearance Information
| ZA Case | Cleared | 5/8/2020 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 5/12/2020 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2020 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 5/19/2020 | ERIK BEASLEY |
| Flood clearance | Cleared | 6/9/2020 | RAYMOND LAM |
Contact Information
| Contractor | Clean Power Management Llc; Lic. No.: 1041123-B | 24941 DANA POINT HARBOR DRIVE SUITE C220 DANA POINT, CA 92629 |
| Engineer | Bushra,, Rafeek L; Lic. No.: S4490 | 2564 W WOODLAND DR ANAHEIM, CA 92801 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2020 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 9/28/2020 | Approved | JOEY BUCHANAN |
| Rough | 10/22/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 12/18/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 12/18/2020 | Approved | JOEY BUCHANAN |
| Final | 7/15/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 7/19/2021 | Permit Finaled | JOEY BUCHANAN |