3696 N GOODLAND AVE 91604
Certificate Information: 3696 N GOODLAND AVE 91604
- Application / Permit
- 20020-10000-00383
- Plan Check / Job No.
- B20LA03196
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Permanent)
- Work Description
- RETAINING WALL SHORING PER SHORING PLAN
- Permit Issued
- Issued on 12/17/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/9/2023
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | DANIEL YIP |
| Corrections Issued | 3/20/2020 | AMIR DANAI |
| Quality Review Completed | 4/1/2020 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 4/27/2021 | DANIEL YIP |
| Plan Check Approved | 7/29/2021 | DANIEL YIP |
| Issued | 12/17/2021 | APPLICANT |
| Building Plans Picked Up | 12/17/2021 | APPLICANT |
| Permit Finaled | 11/9/2023 | MANUEL TEJADA |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 3/3/2020 | AMIR DANAI |
| Grading Pre-Inspection | Cleared | 3/3/2020 | AMIR DANAI |
| Address approval | Cleared | 6/19/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2020 | GABRIEL ROBLES |
| Excavation more than 5-ft deep | Cleared | 7/29/2021 | CALOSHA APPROVED |
| Green Code | Cleared | 7/29/2021 | AMIR DANAI |
Contact Information
| Contractor | Building Green Construction Services; Lic. No.: 947229-B | 12650 RIVERSIDE DRIVE #100 STUDIO CITY, CA 91607 |
| Engineer | Cefali,, David Allen; Lic. No.: S3658 | 4344 LAUREL CANYON BLVD_STE 3 STUDIO CITY, CA 91604 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2022 | Partial Inspection | ARAM AVEDISIAN |
| Deputy Grading | 3/14/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/15/2022 | Approved | TIMOTHY POWELL |
| Piling/Pier/Caisson | 3/15/2022 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 3/16/2022 | Approved | MANUEL TEJADA |
| Piling/Pier/Caisson | 3/16/2022 | Partial Inspection | MANUEL TEJADA |
| Deputy Grading | 3/17/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 3/18/2022 | Approved | MANUEL TEJADA |
| Piling/Pier/Caisson | 3/18/2022 | Partial Approval | MANUEL TEJADA |
| Piling/Pier/Caisson | 3/21/2022 | Partial Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 3/21/2022 | Partial Inspection | TIMOTHY POWELL |
| Piling/Pier/Caisson | 3/22/2022 | Partial Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 3/22/2022 | Partial Inspection | TIMOTHY POWELL |
| Deputy Grading | 3/24/2022 | Approved | TIMOTHY POWELL |
| Deputy Grading | 4/7/2022 | Approved | TIMOTHY POWELL |
| Deputy Steel/Welding | 4/11/2022 | Approved | MANUEL TEJADA |
| Footing/Foundation/Slab | 5/16/2022 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 5/23/2022 | Partial Approval | MANUEL TEJADA |
| Piling/Pier/Caisson | 5/23/2022 | Partial Approval | MANUEL TEJADA |
| Special/Order Compliance | 5/23/2022 | Partial Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 6/6/2022 | No Access for Inspection | MANUEL TEJADA |
| Footing/Foundation/Slab | 6/8/2022 | Corrections Issued | MANUEL TEJADA |
| Special/Order Compliance | 6/14/2022 | Approved | MANUEL TEJADA |
| Special/Order Compliance | 8/18/2022 | Conditional Approval | MANUEL TEJADA |
| Final | 11/7/2023 | Corrections Issued | MANUEL TEJADA |
| Green Building Final | 11/7/2023 | Approved | MANUEL TEJADA |
| Final | 11/8/2023 | Partial Inspection | MANUEL TEJADA |
| Final | 11/9/2023 | Permit Finaled | MANUEL TEJADA |