2657 N LARMAR ROAD 90068
Certificate Information: 2657 N LARMAR ROAD 90068
- Application / Permit
- 20020-10000-00359
- Plan Check / Job No.
- B20LA02996
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Permanent)
- Work Description
- SHORING FOR PROPOSED RETAINING WALL.
- Permit Issued
- Issued on 8/3/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/1/2024
Permit Application Status History
| Submitted | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | JOHNNY WU |
| Corrections Issued | 3/10/2020 | JOHNNY WU |
| Quality Review Completed | 3/10/2020 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 3/12/2020 | APPLICANT |
| Plan Check Approved | 4/13/2020 | JOHNNY WU |
| Issued | 8/3/2020 | APPLICANT |
| Permit Finaled | 11/1/2024 | ALEXANDER HELFER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/10/2020 | JOHNNY WU |
| Work Adjacent to Public Way | Cleared | 3/20/2020 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2020 | ELENA LOPEZ |
| Miscellaneous | Cleared | 4/2/2020 | SARAHI ORTEGA |
| Specific Plan | Cleared | 4/2/2020 | SARAHI ORTEGA |
| ZI | Cleared | 4/2/2020 | SARAHI ORTEGA |
| ZI | Cleared | 4/2/2020 | SARAHI ORTEGA |
| Excavation more than 5-ft deep | Cleared | 4/13/2020 | CALOSHA APPROVED |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Contractor | Owner-Builder | , |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 8/5/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Other (see comments) | 8/5/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/6/2020 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Grading | 8/7/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Piling/Pier/Caisson | 8/10/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Grading | 8/11/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 8/11/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/13/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/17/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/18/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/19/2020 | Approved | VASIL MIHALEV |
| Piling/Pier/Caisson | 8/25/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 8/26/2020 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 8/31/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 9/8/2020 | Approved | VASIL MIHALEV |
| Deputy Grading | 9/9/2020 | Approved | VASIL MIHALEV |
| Deputy Steel/Welding | 9/10/2020 | No Access for Inspection | VASIL MIHALEV |
| Deputy Steel/Welding | 9/14/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 9/18/2020 | Approved | VASIL MIHALEV |
| Special/Order Compliance | 9/18/2020 | Approved | VASIL MIHALEV |
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Approved | VASIL MIHALEV |
| Deputy Shotcrete | 9/28/2020 | Approved | VASIL MIHALEV |
| Pre-Inspection | 9/19/2022 | Not Ready for Inspection | ALEXANDER HELFER |