2633 S VERMONT AVE 90007

Certificate Information: 2633 S VERMONT AVE 90007

Application / Permit
20020-10000-00318
Plan Check / Job No.
B20LA02555
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Fence Wall
Work Description
NEW 8'X26' CMU WALL
Permit Issued
Issued on 6/24/2021
Issuing Office
Current Status
Permit Finaled on 12/10/2021

Permit Application Status History

Submitted 2/10/2020 APPLICANT
Disabled Access Plans Picked Up 3/18/2020 APPLICANT
Assigned to Plan Check Engineer 3/19/2020 MINA HABIB
Corrections Issued 3/26/2020 MINA HABIB
Quality Review Completed 4/13/2020 KESETE HAREGOT
Applicant returned to address corrections 6/24/2020 MINA HABIB
Applicant returned to address corrections 6/25/2020 MINA HABIB
Applicant returned to address corrections 7/16/2020 MINA HABIB
Applicant returned to address corrections 9/2/2020 MINA HABIB
Applicant returned to address corrections 5/10/2021 MINA HABIB
Applicant returned to address corrections 5/11/2021 MINA HABIB
Plan Check Approved 5/13/2021 MINA HABIB
Issued 6/24/2021 APPLICANT
Building Plans Picked Up 6/25/2021 APPLICANT
Permit Finaled 12/9/2021 RUSSELL BONVOULOIR

Permit Application Clearance Information

HPOZ Cleared 6/30/2020 LYDIA CHAPMAN
Miscellaneous Cleared 6/30/2020 LYDIA CHAPMAN
Community Plan Implem. Overlay Cleared 8/18/2020 SANTOS SANCHEZ
ZA Case Cleared 8/18/2020 SANTOS SANCHEZ
ZI Cleared 8/18/2020 SANTOS SANCHEZ
ZI Cleared 8/18/2020 SANTOS SANCHEZ
CPC Cleared 9/2/2020 LYDIA CHAPMAN
DAS Clearance Cleared 5/12/2021 MINA HABIB

Contact Information

Architect Do,, Dung Khac; Lic. No.: C18015 26 EXECUTIVE PARK SUITE 170      IRVINE, CA 92614
Contractor Vantage Company; Lic. No.: 799597-B 1643 W ORANGE GROVE AVE      ORANGE, CA 92868

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/2/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Footing/Foundation/Slab 8/2/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 8/3/2021 Approved JONATHAN QUACH
Footing/Foundation/Slab 8/3/2021 Approved JONATHAN QUACH
Masonry Wall/Backfill 8/6/2021 Approved LEOPOLDO MENDOZA
Final 12/9/2021 Permit Finaled RUSSELL BONVOULOIR