6330 W 3RD ST 90036
Certificate Information: 6330 W 3RD ST 90036
- Application / Permit
- 20020-10000-00191
- Plan Check / Job No.
- B20LA01391
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- CONSTRUCTION OF RETAINING WALL
- Permit Issued
- Issued on 6/12/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/18/2020
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | JESSE ARELLANO |
| Corrections Issued | 3/3/2020 | JESSE ARELLANO |
| Quality Review Completed | 3/16/2020 | BILL STUTSMAN |
| Applicant returned to address corrections | 4/21/2020 | JESSE ARELLANO |
| Building Plans Picked Up | 4/21/2020 | APPLICANT |
| Applicant returned to address corrections | 5/19/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/21/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/27/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/29/2020 | JESSE ARELLANO |
| Plan Check Approved | 6/12/2020 | JESSE ARELLANO |
| Issued | 6/12/2020 | APPLICANT |
| Permit Finaled | 8/18/2020 | TIMOTHY BUXTON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Savant Construction Inc; Lic. No.: 596646-B | 13830 MOUNTAIN AVENUE CHINO, CA 91710 |
| Engineer | Williams,, Warren W; Lic. No.: C43179 | 9912 OAKWOOD CIRCLE VILLA PARK, CA 92861 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2020 | No Access for Inspection | LARRY ARNICK |
| Pre-Inspection | 6/17/2020 | Partial Inspection | JONATHAN QUACH |
| Deputy Grading | 6/23/2020 | Conditional Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 6/23/2020 | Partial Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 6/23/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Grading | 6/24/2020 | Conditional Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 6/24/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Grading | 6/25/2020 | Conditional Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 6/25/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Grading | 6/26/2020 | Conditional Approval | LARRY ARNICK |
| Piling/Pier/Caisson | 6/26/2020 | Partial Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 6/29/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Grading | 6/30/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 6/30/2020 | Conditional Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 6/30/2020 | Partial Inspection | JONATHAN QUACH |
| Deputy Grading | 7/1/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 7/1/2020 | Conditional Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 7/1/2020 | Partial Approval | JONATHAN QUACH |
| Deputy Grading | 7/2/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 7/2/2020 | Conditional Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 7/2/2020 | Conditional Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 7/6/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Piling/Pier/Caisson | 7/6/2020 | Not Ready for Inspection | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 7/7/2020 | Partial Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 7/8/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Partial Approval | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 7/10/2020 | Approved | TIMOTHY BUXTON |
| Deputy Reinf. Masonry | 7/15/2020 | Conditional Approval | JONATHAN QUACH |
| Masonry Wall/Backfill | 7/16/2020 | Partial Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 7/29/2020 | Partial Approval | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 7/29/2020 | Approved | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 8/3/2020 | Partial Approval | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 8/3/2020 | Partial Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 8/4/2020 | Partial Approval | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 8/4/2020 | Partial Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 8/5/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 8/5/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 8/14/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 8/18/2020 | Permit Finaled | TIMOTHY BUXTON |