656 E CALIFORNIA AVE 90291
Certificate Information: 656 E CALIFORNIA AVE 90291
- Application / Permit
- 20020-10000-00156
- Plan Check / Job No.
- B20LA01028
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL 8' X 224' 1 OF 2
- Permit Issued
- Issued on 8/3/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/27/2021
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 3/17/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 3/26/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 4/2/2020 | APPLICANT |
| Applicant returned to address corrections | 7/1/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/21/2020 | SERGIO GUTIERREZ |
| Issued | 8/3/2020 | APPLICANT |
| Permit Finaled | 8/27/2021 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Coastal Zone | Cleared | 5/5/2020 | JOE LUCKEY |
| Miscellaneous | Cleared | 5/5/2020 | JOE LUCKEY |
| Miscellaneous | Cleared | 5/5/2020 | JOE LUCKEY |
| Miscellaneous | Cleared | 5/5/2020 | JOE LUCKEY |
| Specific Plan | Cleared | 5/5/2020 | JOE LUCKEY |
| Specific Plan | Cleared | 5/5/2020 | JOE LUCKEY |
| ZA Case | Cleared | 5/5/2020 | JOE LUCKEY |
| ZA Case | Cleared | 5/5/2020 | JOE LUCKEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/6/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 8/14/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 8/14/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 8/31/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 9/16/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 10/1/2020 | Partial Approval | DAVID HEINE |
| Reinforced Concrete Frame | 10/6/2020 | Partial Approval | DAVID HEINE |
| Reinforced Masonry Frame | 10/6/2020 | Partial Approval | DAVID HEINE |
| Deputy Reinf. Masonry | 10/7/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 10/19/2020 | Partial Approval | DAVID HEINE |
| Deputy Reinf. Masonry | 10/22/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 10/23/2020 | Partial Approval | DAVID HEINE |
| Final | 8/27/2021 | Permit Finaled | JOHNNY MIRANDA |