4200 N RADFORD AVE 91604
Certificate Information: 4200 N RADFORD AVE 91604
- Application / Permit
- 20020-10000-00108
- Plan Check / Job No.
- B20LA00724
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- MECH EQUIPMENT PAD AND ENCLOSURE
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2020 | MICHAEL PEREZ |
| Corrections Issued | 3/2/2020 | MICHAEL PEREZ |
| Quality Review Completed | 3/10/2020 | QUAN NGHIEM |
| Plan Check Approved | 8/11/2020 | MICHAEL PEREZ |
| Issued | 4/29/2022 | APPLICANT |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| CofO in Progress | 12/18/2024 | STEVEN LEVITT |
| CofO in Progress | 12/19/2024 | JEFFREY DURAN |
| CofO Issued | 12/19/2024 | JEFFREY DURAN |
| Permit Finaled | 12/19/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/25/2020 | MAXFIELD VERMY |
| CPC | Cleared | 3/25/2020 | MAXFIELD VERMY |
| CPC | Cleared | 3/25/2020 | MAXFIELD VERMY |
| CPC | Cleared | 3/25/2020 | MAXFIELD VERMY |
| ZA Case | Cleared | 3/25/2020 | MAXFIELD VERMY |
| ZI | Cleared | 3/25/2020 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 4/9/2020 | MITESH PATEL |
| Encroachment in public way | Cleared | 8/4/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | ELENA LOPEZ |
Contact Information
| Contractor | Shea J F Construction Inc; Lic. No.: 769989-A | P O BOX 489 WALNUT, CA 917880489 |
| Engineer | Tang,, Stanley Siu Kei; Lic. No.: C56178 | 1105 N AVON STREET BURBANK, CA 91505 |
| Engineer | Zhang,, Xiaozhe; Lic. No.: S5863 | 13436 ASHWORTH PL CERRITOS, CA 90703 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Footing/Foundation/Slab | 6/6/2024 | Partial Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 6/11/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 6/21/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 6/21/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 6/24/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 6/28/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 6/28/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 7/5/2024 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 7/8/2024 | Approved | STEVEN LEVITT |
| Reinforced Concrete Frame | 7/8/2024 | Approved | STEVEN LEVITT |
| Deputy Reinf. Concrete | 7/9/2024 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/6/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 8/12/2024 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/12/2024 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/16/2024 | Conditional Approval | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 8/21/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 8/27/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Other (see comments) | 8/27/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Masonry | 8/27/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Masonry | 8/28/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 8/30/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Steel/Welding | 8/30/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 9/3/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Steel/Welding | 9/3/2024 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 9/12/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Deputy Reinf. Concrete | 9/13/2024 | Conditional Approval | STEVEN LEVITT |
| Footing/Foundation/Slab | 9/13/2024 | Approved | STEVEN LEVITT |
| Deputy Reinf. Concrete | 9/16/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 9/17/2024 | Conditional Approval | STEVEN LEVITT |
| Deputy Reinf. Concrete | 9/23/2024 | Conditional Approval | CAMERON CHABAN |
| Final | 12/10/2024 | OK to Issue CofO | STEVEN LEVITT |