6609 N GAZETTE AVE 91306

Certificate Information: 6609 N GAZETTE AVE 91306

Application / Permit
20016-90000-08746
Plan Check / Job No.
--
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Reroof with 13 sqrs COMP SHINGLE roofing over new solid sheathing. Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. For residential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by Cool Roof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 149(b). Replace 12 window(s). Same size, location, number, type. Interior kitchen remodel/repair (no changes in walls or openings). Interior bathroom remodel/repair (no changes in walls or openings).
Permit Issued
Issued on 4/2/2020
Issuing Office
Current Status
Permit Finaled on 2/4/2021

Permit Application Status History

Issued 4/2/2020 INTERNET PERMIT
Permit Finaled 2/4/2021 CHRISTOPHER DELLEFIELD

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/24/2020 Approved HENRY KIM
Drywall Nailing 4/24/2020 Approved HENRY KIM
ELECTRICAL-Rough 4/24/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Not Ready for Inspection HENRY KIM
Gas Test 4/24/2020 Approved HENRY KIM
HVAC-Rough 4/24/2020 Approved HENRY KIM
Insulation 4/24/2020 Approved HENRY KIM
Interior/Exterior Lathing 4/24/2020 Approved HENRY KIM
PLUMBING-Rough 4/24/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Approved HENRY KIM
Interior/Exterior Lathing 5/1/2020 Approved HENRY KIM
Shower Pan 5/1/2020 Approved HENRY KIM
Footing/Foundation/Slab 10/27/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 10/27/2020 Not Ready for Inspection HENRY KIM
Underground Mechanical 10/27/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 1/8/2021 Corrections Issued HENRY KIM
Final 1/8/2021 Corrections Issued HENRY KIM
HVAC-Final 1/8/2021 Approved HENRY KIM
PLUMBING-Final 1/8/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/8/2021 SGSOV Approved HENRY KIM
Final 1/14/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 1/26/2021 Approved HENRY KIM
Final 1/26/2021 Not Ready for Inspection HENRY KIM
Final 2/4/2021 Permit Finaled CHRISTOPHER DELLEFIELD