1643 W 38TH ST 90062

Certificate Information: 1643 W 38TH ST 90062

Application / Permit
20016-70000-07858
Plan Check / Job No.
B20SL00471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO REAR OF SINGLE FAMILY DWELLING AND REMODEL.
Permit Issued
Issued on 7/1/2020
Issuing Office
Current Status
CofO Issued on 2/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 ADAM HEGAZI
Corrections Issued 4/14/2020 ADAM HEGAZI
Quality Review Completed 4/17/2020 STANLEY RAAP
Plan Check Approved 7/1/2020 ADAM HEGAZI
Issued 7/1/2020 APPLICANT
Building Plans Picked Up 7/6/2020 APPLICANT
CofO in Progress 1/12/2023 SABAS ALONSO
Permit Finaled 2/4/2023 DEROLD HAUFF
CofO Issued 2/4/2023 DEROLD HAUFF
Permit Finaled 2/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 6/23/2020 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 8/5/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 8/5/2021 Approved SABAS ALONSO
Green Building Rough 8/5/2021 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 8/5/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/29/2021 No Access for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/29/2021 No Access for Inspection SABAS ALONSO
Green Building Rough 10/29/2021 No Access for Inspection SABAS ALONSO
HVAC-Rough 10/29/2021 No Access for Inspection SABAS ALONSO
PLUMBING-Rough 10/29/2021 No Access for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/3/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 11/3/2021 Approved SABAS ALONSO
Green Building Rough 11/3/2021 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 11/3/2021 Approved SABAS ALONSO
PLUMBING-Rough 11/3/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 11/29/2021 No Access for Inspection SABAS ALONSO
Green Building Rough 11/29/2021 No Access for Inspection SABAS ALONSO
Insulation 11/29/2021 Corrections Issued JUSTIN HAWLEY
Shower Pan 11/29/2021 Not Ready for Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 12/27/2021 Corrections Issued SABAS ALONSO
Green Building Rough 12/27/2021 Not Ready for Inspection SABAS ALONSO
Insulation 12/27/2021 Not Ready for Inspection SABAS ALONSO
Shower Pan 12/27/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 2/8/2022 Approved SABAS ALONSO
Green Building Rough 2/8/2022 Approved SABAS ALONSO
Insulation 2/8/2022 Approved SABAS ALONSO
Drywall Nailing 3/15/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 3/15/2022 Approved SABAS ALONSO
Shower Pan 3/15/2022 Corrections Issued SABAS ALONSO
Shower Pan 3/17/2022 Approved SABAS ALONSO
Final 9/16/2022 Corrections Issued SABAS ALONSO
Green Building Final 9/16/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Not Ready SABAS ALONSO
Service/Power Release 9/16/2022 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 9/16/2022 Approved SABAS ALONSO
Final 9/23/2022 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved SABAS ALONSO
Service/Power Release 9/23/2022 Approved SABAS ALONSO
Final 1/6/2023 Corrections Issued SABAS ALONSO
Final 1/11/2023 OK to Issue CofO SABAS ALONSO