3743 S NORTON AVE 90018
Certificate Information: 3743 S NORTON AVE 90018
- Application / Permit
- 20016-70000-06780
- Plan Check / Job No.
- B20SL00394
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND RECREATION ROOM TO ADU.
- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/6/2020 | RICARDO RAMIREZ |
| Corrections Issued | 3/6/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 6/4/2020 | ADAM HEGAZI |
| Issued | 6/24/2020 | LADBS |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| CofO in Progress | 1/20/2021 | DAVID FEILER |
| Permit Finaled | 2/25/2021 | DEROLD HAUFF |
| CofO Issued | 2/25/2021 | DEROLD HAUFF |
| Permit Finaled | 2/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 3/11/2020 | GILBERT URREA |
| Sewer availability | Cleared | 3/11/2020 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 4/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Truebuilt Construction Inc; Lic. No.: 1052087-B | 1944 N TUSTIN ST STE 105 ORANGE, CA 92865 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/8/2020 | Approved | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 7/30/2020 | Partial Approval | COREY HUPP |
| Underground Mechanical | 7/30/2020 | Corrections Issued | COREY HUPP |
| Underground Mechanical | 8/4/2020 | Partial Approval | COREY HUPP |
| Underground Mechanical | 8/10/2020 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 8/18/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 8/18/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 8/26/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 8/26/2020 | Not Ready for Inspection | COREY HUPP |
| Wood Frame | 9/2/2020 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 9/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 9/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 9/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/11/2020 | Partial Approval | COREY HUPP |
| Green Building Rough | 9/11/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 9/21/2020 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 9/25/2020 | Approved | DAVID FEILER |
| Drywall Nailing | 10/6/2020 | Approved | DAVID FEILER |
| HVAC-Final | 12/2/2020 | Corrections Issued | DAVID FEILER |
| Final | 12/15/2020 | Corrections Issued | DAVID FEILER |
| Green Building Final | 12/15/2020 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 12/15/2020 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 1/20/2021 | Approved | DAVID FEILER |
| Final | 1/20/2021 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 1/20/2021 | Approved | DAVID FEILER |
| HVAC-Final | 1/20/2021 | Approved | DAVID FEILER |
| PLUMBING-Final | 1/20/2021 | Approved | DAVID FEILER |