1045 W 73RD ST 90044
Certificate Information: 1045 W 73RD ST 90044
- Application / Permit
- 20016-70000-05618
- Plan Check / Job No.
- B20SL00306
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE INTO ADU.
- Permit Issued
- Issued on 3/9/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/30/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2020 | LUKE GONZALES |
| Corrections Issued | 2/25/2020 | LUKE GONZALES |
| Plan Check Approved | 2/26/2020 | LUKE GONZALES |
| Issued | 3/9/2020 | LADBS |
| CofO in Progress | 5/20/2020 | EUGENE CASSIDY |
| Permit Finaled | 7/30/2020 | DEROLD HAUFF |
| CofO Issued | 7/30/2020 | DEROLD HAUFF |
| Permit Finaled | 7/30/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2020 | JAMES MORALEZ |
| Construction near power lines | Cleared | 2/26/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 2/26/2020 | ROBERT DUFF |
| Sewer availability | Cleared | 2/26/2020 | JAMES MORALEZ |
| ZI | Cleared | 2/26/2020 | JOSE ROMERO-NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 3/16/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/20/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/20/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 3/20/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/24/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 3/24/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/24/2020 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/1/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/1/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 4/1/2020 | Approved | EUGENE CASSIDY |
| Insulation | 4/3/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/3/2020 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 4/6/2020 | Approved | EUGENE CASSIDY |
| Shower Pan | 4/6/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 5/11/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 5/11/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 5/11/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 5/11/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/11/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 5/11/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/18/2020 | Approved | EUGENE CASSIDY |
| Final | 5/18/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 5/18/2020 | Approved | EUGENE CASSIDY |
| Final | 5/20/2020 | OK to Issue CofO | EUGENE CASSIDY |