1669-1669 1/2 E 111TH PL 90059

Certificate Information: 1669-1669 1/2 E 111TH PL 90059

Application / Permit
20016-70000-02751
Plan Check / Job No.
B20SL00152
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN ATTACHED 2 CAR GARAGE INTO AN ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 2/20/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 10/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 LUKE GONZALES
Corrections Issued 1/30/2020 LUKE GONZALES
Plan Check Approved 2/20/2020 RICARDO RAMIREZ
Issued 2/20/2020 LADBS
CofO in Progress 8/27/2020 EUGENE CASSIDY
Permit Finaled 10/7/2020 DEROLD HAUFF
CofO Issued 10/7/2020 DEROLD HAUFF
Permit Finaled 10/7/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/20/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/20/2020 PAMELA TENEZA
Hydrant and Access approval Cleared 2/20/2020 GEORGE SUCHAND
Sewer availability Cleared 2/20/2020 THOMAS LANG
ZI Cleared 2/20/2020 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/4/2020 Corrections Issued WILLIAM ROSE
BUILDING-Rough-Frame 4/1/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/23/2020 Not Ready for Inspection BRIAN CHRISTIAN
HVAC-Rough 4/23/2020 Approved BRIAN CHRISTIAN
PLUMBING-Rough 4/23/2020 Not Ready for Inspection BRIAN CHRISTIAN
ELECTRICAL-Rough 5/1/2020 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 5/1/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 5/1/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 5/5/2020 Corrections Issued EUGENE CASSIDY
HVAC-Rough 5/5/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/5/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/6/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/6/2020 Approved EUGENE CASSIDY
Insulation 5/8/2020 Approved EUGENE CASSIDY
Drywall Nailing 6/2/2020 Corrections Issued BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/3/2020 Approved BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 6/3/2020 Partial Approval BRIAN CHRISTIAN
Drywall Nailing 6/5/2020 Approved EUGENE CASSIDY
Gas Test 6/5/2020 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 6/5/2020 Approved EUGENE CASSIDY
Shower Pan 6/5/2020 Approved EUGENE CASSIDY
Final 7/24/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 7/24/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/24/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 7/24/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/4/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/4/2020 Approved EUGENE CASSIDY
Smoke Detectors 8/4/2020 Approved EUGENE CASSIDY
Drywall Nailing 8/5/2020 Approved EUGENE CASSIDY
Final 8/10/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 8/10/2020 Corrections Issued EUGENE CASSIDY
Final 8/19/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 8/19/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/27/2020 Approved EUGENE CASSIDY
Final 8/27/2020 OK to Issue CofO EUGENE CASSIDY
Green Building Final 8/27/2020 Approved EUGENE CASSIDY
HVAC-Final 8/27/2020 Approved EUGENE CASSIDY
PLUMBING-Final 8/27/2020 Approved EUGENE CASSIDY