2184 W 30TH ST 90018
Certificate Information: 2184 W 30TH ST 90018
- Application / Permit
- 20016-70000-02468
- Plan Check / Job No.
- B20SL00143
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ALTERATION/CONVERSION OF (E) GARAGE/REC ROOM INTO AN ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 5/12/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2020 | LUKE GONZALES |
| Corrections Issued | 1/28/2020 | LUKE GONZALES |
| Plan Check Approved | 3/6/2020 | RICARDO RAMIREZ |
| Issued | 5/12/2020 | LADBS |
| Building Plans Picked Up | 5/13/2020 | APPLICANT |
| CofO in Progress | 4/8/2021 | ROBERT MCDOWELL |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
| CofO Issued | 5/1/2021 | DEROLD HAUFF |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2020 | EMIL KYUPELYAN |
| Construction near power lines | Cleared | 1/29/2020 | OSCAR CASTRO |
| Sewer availability | Cleared | 1/29/2020 | EMIL KYUPELYAN |
| ZI | Cleared | 1/29/2020 | TERRI OSBORNE |
| HPOZ | Cleared | 2/5/2020 | MAX LODER |
| ZI | Cleared | 2/5/2020 | MAX LODER |
| ZI | Cleared | 2/5/2020 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 3/2/2020 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/2/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/2/2020 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 7/2/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| METHANE-Rough | 7/2/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/8/2020 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 7/15/2020 | Corrections Issued | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 7/15/2020 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 7/15/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/28/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 7/28/2020 | Corrections Issued | ROBERT MCDOWELL |
| Green Building Rough | 7/28/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Rough | 7/28/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/28/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 8/17/2020 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/17/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 8/20/2020 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 9/2/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Final | 9/11/2020 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Final | 11/6/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Final | 11/6/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Final | 11/17/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 11/17/2020 | Approved | ROBERT MCDOWELL |
| Gas Test | 12/8/2020 | Approved | ROBERT MCDOWELL |
| Service/Power Release | 12/8/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/8/2021 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/8/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/8/2021 | Approved | ROBERT MCDOWELL |