6308 S KENISTON AVE 90043

Certificate Information: 6308 S KENISTON AVE 90043

Application / Permit
20016-70000-01988
Plan Check / Job No.
B20SL00112
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ADU.
Permit Issued
Issued on 2/28/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 4/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 RICARDO RAMIREZ
Corrections Issued 1/23/2020 RICARDO RAMIREZ
Plan Check Approved 2/28/2020 TEODORO DIAZ RODRIGUEZ
Issued 2/28/2020 LADBS
CofO in Progress 3/12/2021 FREDDIE RIVERA
Permit Finaled 4/20/2021 DEROLD HAUFF
CofO Issued 4/20/2021 DEROLD HAUFF
Permit Finaled 4/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/14/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JUAN ASHTON
Sewer availability Cleared 2/14/2020 JUAN ASHTON
Hydrant and Access approval Cleared 2/19/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/12/2020 Not Ready for Inspection FREDDIE RIVERA
Pre-Inspection 6/12/2020 Corrections Issued FREDDIE RIVERA
Wood Frame 6/12/2020 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 6/17/2020 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 6/23/2020 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 6/29/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 7/21/2020 Corrections Issued JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Corrections Issued JOSEPH MCGARRY
HVAC-Rough 7/21/2020 Corrections Issued JOSEPH MCGARRY
Underground Mechanical 7/21/2020 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Rough 7/30/2020 Approved FREDDIE RIVERA
Gas Test 7/30/2020 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 7/30/2020 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 8/26/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 8/26/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 8/26/2020 Approved FREDDIE RIVERA
Underground Mechanical 8/26/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/8/2020 Approved FREDDIE RIVERA
Gas Test 9/8/2020 Approved FREDDIE RIVERA
Insulation 9/8/2020 Approved FREDDIE RIVERA
Underground Mechanical 9/8/2020 Approved FREDDIE RIVERA
Drywall Nailing 9/15/2020 Approved FREDDIE RIVERA
Final 12/2/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 12/2/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/2/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 12/2/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Not Ready FREDDIE RIVERA
Final 3/11/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 3/11/2021 Approved FREDDIE RIVERA
PLUMBING-Final 3/11/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Approved FREDDIE RIVERA
Final 3/12/2021 OK to Issue CofO FREDDIE RIVERA