1611 W 42ND PL 90062

Certificate Information: 1611 W 42ND PL 90062

Application / Permit
20016-70000-00396
Plan Check / Job No.
B20SL00026
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO DETACHED ADU PER ORDINANCE
Permit Issued
Issued on 11/5/2020
Issuing Office
Current Status
CofO Issued on 5/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/17/2020 AMIR DANAI
Corrections Issued 7/17/2020 AMIR DANAI
Applicant returned to address corrections 8/11/2020 HELEN NGUYEN
Plan Check Approved 10/28/2020 SINA KHOSRAVI
Issued 11/5/2020 APPLICANT
Building Plans Picked Up 11/6/2020 APPLICANT
CofO in Progress 4/29/2021 ROBERT MCDOWELL
Permit Finaled 5/13/2021 DEROLD HAUFF
CofO Issued 5/13/2021 DEROLD HAUFF
Permit Finaled 5/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 2/8/2020 RIDWAN HARDY
Address approval Cleared 8/21/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/21/2020 RENZ SORIANO
Permit Cleared 8/21/2020 RENZ SORIANO
Sewer availability Cleared 8/21/2020 RENZ SORIANO
Low Impact Development Cleared 10/14/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/14/2020 RENZ SORIANO
Trees in Parkway Cleared 10/22/2020 JOHN KIM
Green Code Cleared 10/28/2020 AMIR DANAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/5/2021 Corrections Issued ROBERT MCDOWELL
ELECTRICAL-Rough 2/5/2021 Not Ready for Inspection ROBERT MCDOWELL
Green Building Rough 2/5/2021 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Rough 2/5/2021 Not Ready for Inspection ROBERT MCDOWELL
PLUMBING-Rough 2/5/2021 Not Ready for Inspection ROBERT MCDOWELL
PLUMBING-Rough 2/12/2021 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 2/16/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 2/16/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 2/16/2021 Approved ROBERT MCDOWELL
Insulation 2/22/2021 Not Ready for Inspection ROBERT MCDOWELL
Insulation 3/9/2021 Approved ROBERT MCDOWELL
Drywall Nailing 3/17/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 4/29/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 4/29/2021 Approved ROBERT MCDOWELL
Final 4/29/2021 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 4/29/2021 Approved ROBERT MCDOWELL
Green Building Rough 4/29/2021 Approved ROBERT MCDOWELL
HVAC-Final 4/29/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/29/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Approved ROBERT MCDOWELL
Service/Power Release 4/29/2021 Approved ROBERT MCDOWELL
Smoke Detectors 4/29/2021 Approved ROBERT MCDOWELL