CONVERT GARAGE AND STORAGE ROOM TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 3/18/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 6/22/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Assigned to Plan Check Engineer 1/3/2020 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 2/21/2020 LUKE GONZALES
Issued 3/18/2020 LADBS
CofO in Progress 6/17/2020 RUBEN SALAS
Permit Finaled 6/22/2020 DEROLD HAUFF
CofO Issued 6/22/2020 DEROLD HAUFF
Permit Finaled 6/22/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/7/2020 ERIK BEASLEY
Sewer availability Cleared 1/7/2020 ERIK BEASLEY
Construction within easement Cleared 2/19/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/23/2020 Corrections Issued RUBEN SALAS
Deputy Drilled-In Anchors 3/23/2020 Partial Approval RUBEN SALAS
Green Building Rough 3/23/2020 Not Ready for Inspection RUBEN SALAS
MERV13>=Rough 3/23/2020 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 3/23/2020 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 3/31/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 3/31/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/31/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 4/2/2020 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 4/2/2020 Corrections Issued SCOTT FINNILA
Green Building Rough 4/2/2020 Partial Inspection SCOTT FINNILA
HVAC-Final 4/2/2020 Corrections Issued SCOTT FINNILA
MERV13>=Rough 4/2/2020 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 4/2/2020 Partial Inspection SCOTT FINNILA
Wood Frame 4/2/2020 Partial Inspection SCOTT FINNILA
ELECTRICAL-Rough 4/3/2020 Approved GORDON ZUBER
ELECTRICAL-Rough 4/8/2020 Approved SCOTT FINNILA
Footing/Foundation/Slab 4/8/2020 Corrections Issued SCOTT FINNILA
Wood Frame 4/8/2020 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 4/15/2020 Corrections Issued KATHRYN BUTTERWORTH
Insulation 4/15/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 4/15/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 No Access for Inspection DAVID CHAN
Footing/Foundation/Slab 4/16/2020 No Access for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 4/20/2020 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 4/20/2020 Partial Approval COREY HUPP
HVAC-Final 4/20/2020 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 5/8/2020 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Final 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Rough 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/15/2020 Conditional Approval SCOTT FINNILA
Final 5/15/2020 Corrections Issued SCOTT FINNILA
Green Building Final 5/15/2020 Conditional Approval SCOTT FINNILA
Green Building Rough 5/15/2020 Conditional Approval SCOTT FINNILA
MERV13>=Final 5/15/2020 Conditional Approval SCOTT FINNILA
MERV13>=Rough 5/15/2020 Conditional Approval SCOTT FINNILA
Smoke Detectors 5/15/2020 Approved SCOTT FINNILA
Special/Order Compliance 5/29/2020 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 6/12/2020 Approved RUBEN SALAS
Final 6/12/2020 Conditional Approval RUBEN SALAS
Green Building Final 6/12/2020 Approved RUBEN SALAS
Green Building Rough 6/12/2020 Approved RUBEN SALAS
MERV13>=Final 6/12/2020 Approved RUBEN SALAS
MERV13>=Rough 6/12/2020 Approved RUBEN SALAS