2112 S HIGHLAND DR 90016
Certificate Information: 2112 S HIGHLAND DR 90016
- Application / Permit
- 20016-70000-00075
- Plan Check / Job No.
- B20SL00007
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT PORTION OF (E) GARAGE (3 OF 5-CAR GARAGE) TO ACCESSORY DWELLING UNIT. EXISTING SFD ON 2ND FLOOR AND 2-CAR GARAGE TO REMAIN. TOTAL 769 SF FOR ADU.
- Permit Issued
- Issued on 10/25/2021
- Issuing Office
- Current Status
- CofO Issued on 6/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2020 | APPLICANT |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | LAURA DUONG |
| Corrections Issued | 2/21/2020 | LAURA DUONG |
| Quality Review Completed | 2/24/2020 | KEN GILL |
| Building Plans Picked Up | 3/2/2020 | APPLICANT |
| Applicant returned to address corrections | 5/1/2020 | LAURA DUONG |
| Applicant returned to address corrections | 6/1/2020 | LAURA DUONG |
| Plan Check Approved | 6/15/2020 | LAURA DUONG |
| Issued | 10/25/2021 | APPLICANT |
| CofO in Progress | 5/6/2022 | STUART CHAPMAN |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
| CofO Issued | 6/23/2022 | DEROLD HAUFF |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/12/2020 | THOMAS LANG |
| Green Code | Cleared | 4/9/2020 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | ANTHONY MAINEZ |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 3/8/2022 | Conditional Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/9/2022 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/14/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 3/15/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/15/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 3/17/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 3/17/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 3/22/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 3/22/2022 | Approved | STUART CHAPMAN |
| Insulation | 3/24/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 3/30/2022 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 4/1/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Final | 4/22/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/22/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 4/22/2022 | Approved | STUART CHAPMAN |
| Final | 4/28/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Approved | STUART CHAPMAN |
| Final | 5/3/2022 | Partial Approval | STUART CHAPMAN |
| Final | 5/6/2022 | OK to Issue CofO | STUART CHAPMAN |